A beginner’s guide to Earned Value Management | Nulab (2024)

Earned Value Management (or EVM for short) is a technique that’s essentially the gold standard for managing a project’s schedule and budget. In fact, it’s so highly regarded and so effective at scale that the United States government uses it to measure and manage the performance of its programs. So what is it?

What is Earned Value Management?

EVM is a tool that helps us understand project performance in terms of cost and schedule at the same time. It also helps us predict how a project will perform if we carry on as we are.

There are four main components to EVM that help us understand how a project is or could potentially perform.

1. Budget at completion

This represents the budgeted cost of the project. It can be current, as in the approved budget for something performed during a given time period. Or it can be cumulative — i.e., the sum of all budgeted activities scheduled up to a certain date.

2. Budgeted cost of work scheduled (aka Planned Value, or PV for short)

This is the budgeted cost of work your team will perform according to plan. Again, you can view this cumulatively or to your current state.

3. Budgeted cost of work performed (aka Earned Value, or EV for short)

This is the budgeted value of all the tasks that have been completed up until now.

4. Actual cost of work completed

This is a measure of the total amount of actual expenditure of tasks completed to date. As with the others, you can look at it as a cumulative or current figure.

Why is Earned Value Management important?

EVM lets us work out burn rates for cost and performance, which helps us understand how well the project is performing in relation to the original plan.

Looking at all of these different elements also allows us to look at a project that’s not on schedule or budget (either over or under) and see what the performance is for both of those things simultaneously.

When we take these indices and apply them to the rest of the project (or future work), we can more easily forecast how things will run in terms of cost, performance, and scheduling — assuming the burn rate doesn’t fluctuate.

But remember — this is a big assumption, so it’s important to be flexible and aware of how changes will impact these elements.

So to recap, Earned Value Management helps us work out:

  • Where have we been?
  • Where are we now?
  • And, where are we going?

How to do an Earned Value Analysis

Conducting an Earned Value Analysis is a project in itself. And like all good projects, it needs a plan.

At its most basic, you need to include the following:

  • Scope (major deliverables, project objectives, project assumptions, project constraints, and a statement of work)
  • Work breakdown structure (WBS)

Once you have the foundations of your EVA completed, you need to establish the following three areas:

  • Planned Value (what was the budget you planned for?)
  • Actual Cost (what has your project cost to date?)
  • Earned Value (what has your project earned or accomplished so far?)

You can find this information out by tracking budgets, spending, and schedules. If you use project management software, finding and tracking this information should be relatively easy. If not, speak to accounts, delve into your team’s schedule, and speak to your team members.

Planned Value (PV) is determined by the cost and schedule baseline. Actual Cost (AC) is determined by the real cost incurred. Earned Value (EV) tells you what the project accomplished, earnings-wise.

What’s costing or helping you?

If you came out with a positive number— great job! If you weren’t achieving this conscientiously, here are a few of the factors that could be helping you:

  1. Finding efficiencies— you managed to find a few ways to make the work easier.
  2. Work was simpler— there was an error of judgment of the work to begin with.
  3. Few edits— you did well and hit the mark on the first or second try.
  4. Fluctuations that reduced cost — over the course of the project, maybe a software you needed got cheaper, or you found freelancers with cheaper rates.
  5. Cost decreases — your overhead costs decrease.

Conversely, if you came out with a negative number, here are a few things that may be holding you back that you can work to fix:

  1. Work turned out to be more complex— someone misjudged the complexity of the project at the outset.
  2. Big/many edits — that could be because the project wasn’t done correctly or the needs changed during the work.
  3. Lack of clarity— the parameters weren’t set out well enough at the beginning.
  4. Scope creep — the project accumulates more features or tasks while working.
  5. Cost changes— the labor or materials needed turned out to be more expensive than they were when you started.
  6. Rate increases— the overheard costs went up.

How to work out variances

After the above three values have been established, you can perform what’s known as a ‘variance analysis.’

The aim here is to apply a range to your figures, which helps with planning and budgeting. It’s also useful to show stakeholders, so they have a better idea of what to expect as the project progresses.

There are two different types of variance analysis. Those arethecost and the schedule.

Cost Variance

This is the difference between the Earned Value and Actual Costs. This is used to help you budget and give stakeholders a better understanding of where you stand on the financial side of things. Here’s the formula for working this out:

Cost variance = Earned value – Actual cost

If you get a 0, then you’re on budget. Anything in the negative means you’re over, and a positive value puts you under budget.

Schedule Variance

Schedule Variance tells you whether you’re ahead or behind schedule by looking at the monetary value difference between future and past work. It doesn’t show you the impact of this, nor does it help you identify the source of this difference. Instead, it’s there to help you monitor progress and inform your decision-making. Use the following formula to help you work this out:

Schedule variance = Earned value – Planned value

If your answer is 0, then congratulations! You’re on track. If you have a negative answer, you’re behind schedule, and if it’s positive, then you’re ahead of schedule — which is the best possible outcome.

Find out your performance indexes

A performance index shows you the project’s burn rate, aka how fast it’s burning through the budget. It’s useful to know this because it helps you forecast and adjust accordingly.

  • Schedule Performance Index helps you measure efficiency. It is the ratio of earned value (EV) to planned value (PV). The formula for this is Earned Value / (divided by) Planned Value. A number higher than 1 means performance is going well. Anything underneath 1 means things aren’t going as well as planned.
  • Cost Performance Index helps you measure cost efficiency. It is the ratio of earned value (EV) to actual costs (AC). The formula for this is Earned Value – Actual Costs. A result greater than 1 indicates good cost-efficiency. Anything underneath shows low cost-efficiency.

How to predict the future (of your project)

Once you have all these values, you can start to forecast. To do this, you need to work out when the project finishes and how much budget you need to complete it.

Look at the Estimate At Completion (or EAC for short) and the Budget at Completion (BAC).

The BAC is the total of every single budget you allocate to the project. Remember, it should always equal the same as the project’s Total Value. If not, your analysis will be inaccurate.

The EAC is the actual cost to date and an estimate for the completion of the remaining work. The goal here is to accurately predict the cost at project completion.

There are several formulas you can use to help you work this out. The following is a popular option:

Budget at completion, divided by the current CPI of the project. (EAC = BAC/CPI)

  • Do your EAC and BAC every month or when your project goes through a big change.
  • If your project is ongoing, prepare a comprehensive EAC annually, biannually, or quarterly. Whichever works best for you.

Earned Value Management Checklist

  1. Create a project scope and work breakdown structure. Give each task a WBS number to help with organization.
  2. Schedule tasks and allocate budgets.
  3. Establish your objectives to help you measure progress.
  4. Keep a firm grip on the project’s progress by analyzing costs and variances.
  5. Perform corrective measures to keep your project on track.

Final thoughts

Earned Value Management is a multifaceted technique, and there are several ways you can go about it. To have the biggest chance of success, proper preparation is key. Set some time aside to create a plan, and invest in project management software. Not only does it help you track progress while you’re in the middle of a project. It’s also helpful for collecting schedule and cost information so that when the time comes to conduct your EVM analysis, you’ll have everything you need at your fingertips.

This post was originally published on November 15, 2019, and updated most recently on May 25, 2021.

A beginner’s guide to Earned Value Management | Nulab (2024)

FAQs

What is earned value management for beginners? ›

What is Earned Value Management? Earned value management (EVM) is a project management methodology that integrates schedule, costs, and scope to measure project performance. Based on planned and actual values, EVM predicts the future and enables project managers to adjust accordingly.

What is the basic EVM? ›

Essentially, EVM measures project performance against the baselines outlined in your project scope management plan. Using your original goals as benchmarks, you can measure progress more accurately and draw actionable conclusions.

What is the 0 100 rule in earned value management? ›

Using the 0/100 rule, no credit is earned for an element of work until it is finished. A related rule is called the 50/50 rule, which means 50% credit is earned when an element of work is started, and the remaining 50% is earned upon completion.

What is the difference between EVA and EVM? ›

The Earned Value Management (EVM) method combines cost, schedule, technical scope, and risk aspects within Earned Value Analysis (EVA) to gauge the actual progress of work accomplished in a project. Earned value also defined as the budgeted cost of worked performed (BCWP) helps to compute Performance indices.

What are the three basic metrics of Earned Value Management? ›

EVM is built on three metrics: Planned value, earned value, and actual cost. Think of these metrics in terms of your project budget and schedule.

What is the 50 50 rule in project management? ›

With the 50/50 rule, managers assess 50% of a project's value at the start and 50% when it's complete. So, for example, if a project team is working on a fence that goes around an entire property, they can use their progress on the first portion of the fence to expect their total time and spend.

What is the EVM formula? ›

EV = BAC * Actual % Complete, where BAC is the Budget at Completion, and Actual % Complete is the percentage of actual work completed up to the current reporting period.

What is an EVM example? ›

Earned value management example – 1. Let's imagine we are building a wind power plant. The project is set to be completed in 10 months with an estimated cost of $500,000. The project has been running for 5 months now, the team has spent $220,000 and completed an amount of work worth $255,000.

Why is it difficult to use EVM? ›

Implementing EVM requires careful planning and a structured approach. Project managers often find it challenging to set up the necessary systems and processes to collect accurate data for EVM calculations.

How do you read Earned Value Management? ›

Simply put, it's a quick way to tell if you're behind schedule or over budget on your project. You can calculate the EV of a project by multiplying the percentage complete by the total project budget. For example, let's say you're 60% done, and your project budget is $100,000 — your earned value is then $60,000.

How do you calculate earned value? ›

Earned value can be computed this way : Eearned Value = Percent complete (actual) x Task Budget. For example, if the actual percent complete is 50% and the task budget is $10,000 then the earned value of the project is $5,000, 50% of the budget provided for this project.

What is the CPI for earned value management? ›

It is the ratio of earned value (EV) to actual costs (AC). The CPI is equal to the earned value divided by the actual costs, CPI = EV – AC.” (PMI, 2004, p. 356 A CPI equal to or greater than one indicates a favorable condition and a value of less than one indicates an unfavorable condition.

What is earned value for dummies? ›

The definition of earned value management for dummies

Time - Comparing the amount of work which has been done compared to what was scheduled (are we going to deliver in time?) Cost - Comparing the amount we have spent to the original project budget (have we spent more or less than we had planned)

What are the three dimensions of EVM? ›

The three pillars for EVM are: scope, budget over time and progress data. From the schedule, you can determine the Planned Value (PV) – the work scheduled to be completed by a specific date - and compare it to Earned Value (EV), the budget for the amount of work completed.

How to create an earned value chart in Excel? ›

Choose View > Table, then choose More Tables. In the list, select Earned Value, Earned Value Cost Indicators, or Earned Value Schedule Indicators. If you're not sure which table, just pick Earned Value. Choose Apply.

What is Earned Value Management example? ›

Simply put, it's a quick way to tell if you're behind schedule or over budget on your project. You can calculate the EV of a project by multiplying the percentage complete by the total project budget. For example, let's say you're 60% done, and your project budget is $100,000 — your earned value is then $60,000.

What are the basic elements of earned value management? ›

EVM consists of the following three basic elements: Planned Value. Actual Cost. Earned Value.

What is Earned Value Management and why is it important? ›

Earned value management helps identify problems when they occur. It also allows anticipating the risks associated with the project budget and schedule. Accordingly, managers can intervene and take early actions before experiencing any setbacks.

Top Articles
What are Non-Qualified Plans (W-2)? | BambooHR
The Rule of Thirds: Photographic Composition in Real Estate Photography
Craigslist Livingston Montana
Great Clips Mount Airy Nc
Ohio Houses With Land for Sale - 1,591 Properties
Duralast Gold Cv Axle
Bild Poster Ikea
Amc Near My Location
Instructional Resources
Pga Scores Cbs
Mcfarland Usa 123Movies
Arkansas Gazette Sudoku
Tiger Island Hunting Club
Azeroth Pilot Reloaded - Addons - World of Warcraft
Https://Gw.mybeacon.its.state.nc.us/App
Hair Love Salon Bradley Beach
Who called you from 6466062860 (+16466062860) ?
Divina Rapsing
Ally Joann
Conan Exiles: Nahrung und Trinken finden und herstellen
Putin advierte que si se permite a Ucrania usar misiles de largo alcance, los países de la OTAN estarán en guerra con Rusia - BBC News Mundo
Pocono Recird Obits
D2L Brightspace Clc
Devotion Showtimes Near Regency Buenaventura 6
Workshops - Canadian Dam Association (CDA-ACB)
27 Modern Dining Room Ideas You'll Want to Try ASAP
As families searched, a Texas medical school cut up their loved ones
Wku Lpn To Rn
San Jac Email Log In
Blush Bootcamp Olathe
25Cc To Tbsp
Life Insurance Policies | New York Life
Swgoh Boba Fett Counter
Flixtor Nu Not Working
2024 Coachella Predictions
Moxfield Deck Builder
Prima Healthcare Columbiana Ohio
Vip Lounge Odu
The Bold And The Beautiful Recaps Soap Central
The Syracuse Journal-Democrat from Syracuse, Nebraska
Claim loopt uit op pr-drama voor Hohenzollern
craigslist | michigan
Paperless Employee/Kiewit Pay Statements
Worcester County Circuit Court
Jetblue 1919
Tableaux, mobilier et objets d'art
Grand Valley State University Library Hours
St Vrain Schoology
6463896344
The Plug Las Vegas Dispensary
Coleman Funeral Home Olive Branch Ms Obituaries
Runelite Ground Markers
Latest Posts
Article information

Author: Delena Feil

Last Updated:

Views: 6246

Rating: 4.4 / 5 (65 voted)

Reviews: 88% of readers found this page helpful

Author information

Name: Delena Feil

Birthday: 1998-08-29

Address: 747 Lubowitz Run, Sidmouth, HI 90646-5543

Phone: +99513241752844

Job: Design Supervisor

Hobby: Digital arts, Lacemaking, Air sports, Running, Scouting, Shooting, Puzzles

Introduction: My name is Delena Feil, I am a clean, splendid, calm, fancy, jolly, bright, faithful person who loves writing and wants to share my knowledge and understanding with you.