How to Calculate Earned Value in Project Management (2024)

Back to FAQ

Advanced Terminology

How to Calculate Earned Value in Project Management

Earned value management (EVM) is a method used in project management to assess project performance. It provides valuable insights into the project’s health by measuring the planned work against actual work completed as well as the associated costs.

By calculating the earned value of a project, project managers can monitor progress, identify deviations from the plan, and make necessary adjustments to get the project back on track.

In this article, we will delve into the fundamentals of EVM and guide you through the step-by-step process of how to calculate earned value in project management. Before we begin, you can unlock a free trial with Wrike now to streamline your projects in one platform.

How to Calculate Earned Value in Project Management (1)

What is earned value?

Earned value (EV) is a way to measure and monitor the level of work completed on a project against the plan. Simply put, it’s a quick way to tell if you’re behind schedule or over budget on your project.

You can calculate the EV of a project by multiplying the percentage complete by the total project budget. For example, let’s say you’re 60% done, and your project budget is $100,000 — your earned value is then $60,000. However, to properly use earned value, a few additional calculations must be considered. The largest benefits of earned value result from completing both cost and schedule variance analyses.

Streamline all your projects and track budgets in one platform

Earned value calculations in project management

1. Schedule Variance (SV): Schedule variance is the difference between your planned progress and your actual progress to date. The SV calculation is EV (earned value) - PV (planned value). Let’s assume you have a four-month-long project, and you’re two months in, but the project is only 25% complete. In this case, your EV = 1 months (25% of four months), and your PV = 2 months. Therefore your SV is 1 - 2 = -1. Since the number is negative, it indicates you’re behind schedule.

2. Cost Variance (CV): Similar to SV, cost variance is the difference between how much you planned on spending thus far and your actual costs to date. The CV calculation is: CV = EV - AC (actual cost). Let’s use the earlier example. Your project budget is $100,000 and you’re 60% done, which means your EV is $60,000. If you’ve spent $70,000 so far to get to this point in the project, your CV is -$10,000. You can tell you’re over budget because the number is negative, which may indicate a problem with the project or that the project could go over budget or run out of money.

3. Schedule Performance Index (SPI): This measure is similar to SV but is often preferred as it translates the numbers into a value that is easily compared across tasks or projects. The SPI calculation is: SPI = EV/PV. When SPI is above 1.00, you’re ahead of schedule. If it’s below 1.00, you’re behind. To take the example from above, SPI would be 1/2 = 0.5. Using SPI is different than simply comparing your progress against your baseline. Comparing your actual schedule against your plan may indicate you’re behind on two tasks. So, you know where your immediate problem is, but not necessarily how it impacts the overall project or your expected completion date. Using earned value, you can calculate your SPI both by task and for the project as a whole. When you take the SPI for each task and look at the bigger picture, you can see that your project is ahead of schedule, even with two late tasks. This helps you better understand the overall impact of the late tasks on the project.

How to Calculate Earned Value in Project Management (4)How to Calculate Earned Value in Project Management (5)

4. Cost Performance Index (CPI): As with SPI, CPI allows you to simplify the answer for better analysis. The CPI calculation is: CPI = EV/AC. When CPI is over 1.00, you’re under budget, and when it’s under 1.00, you’re overspending. In the scenario above, CPI = 60,000/ 70,000 = 0.86, indicating an overspend. CPI can be used to forecast your project’s completion. For example, you can divide your total project budget by your current CPI to get the expected total cost at completion. The formula is Estimate at Completion (EAC) = Budget/ CPI. In the above example, this would be $100,000/ 0.86 = $116,279.07. Meaning, that at this point in the project, based on current trends, you will likely end up overspending your budget by $16,279.07. Knowing this early allows you the time to either find ways to cut costs or secure more funding.

Keep track of your project data with Wrike

In conclusion, EVM is a useful technique in project management that enables project managers to accurately assess a project’s performance. The process of calculating EV may seem complex at first but, as we’ve seen, this can easily be overcome with the right tools and techniques.

As monitoring your project is key to delivering a successful outcome, using a robust work management platform can make all the difference. With Wrike, you can easily track, control, and adjust the details of your project, from EV data to schedules.

Further reading

  • Project Management Basics: 6 Steps to a Foolproof Project Plan
  • Why Managers Have Unrealistic Expectations About Their Team’s Capabilities
  • 80+ Awesome Online Resources for Project Managers
  • How to Create a Monthly Budget Spreadsheet Template for Your Small Business

Advanced Terminology

5 questions

What Is Change Management in Project Management? What Is Cost-Benefit Analysis in Project Management? What is Cost Control in Project Management? What is Cost Management in Project Management? What is Cost Variance in Project Management?

#project management #earned value management #evm #schedule variance #cost variance #schedule performance index #cost performance index #cpi #budget

How to Calculate Earned Value in Project Management (2024)

FAQs

How to Calculate Earned Value in Project Management? ›

Earned value can be computed this way : Eearned Value = Percent complete (actual) x Task Budget. For example, if the actual percent complete is 50% and the task budget is $10,000 then the earned value of the project is $5,000, 50% of the budget provided for this project.

What is the formula for earned value? ›

EV = BAC * Actual % Complete, where BAC is the Budget at Completion, and Actual % Complete is the percentage of actual work completed up to the current reporting period.

What is earned value in project management? ›

Earned Value Analysis (EVA) is a method that allows the project manager to measure the amount of work actually performed on a project beyond the basic review of cost and schedule reports. EVA provides a method that permits the project to be measured by progress achieved.

How do you calculate EV in PMP? ›

You can calculate the EV of a project by multiplying the percentage complete by the total project budget. For example, let's say you're 60% done, and your project budget is $100,000 — your earned value is then $60,000.

How to calculate cev in project management? ›

CEV (Cumulative earned value): It is the worth of actual performance over a period of time. It is calculated by multiplying the total budgeted cost by the percentage of work anticipated to be completed.

How to calculate EMV in project management? ›

Let's say there's a 10% chance of your project being impacted by an earthquake to the tune of $1,000,000, then you would calculate EMV using the following steps: Probability of risk = 10% Financial impact of risk = $1,000,000. EMV = Probability x Impact.

What is the formula for EVA in project management? ›

EVA is calculated by taking net operating profit minus a finance charge. The finance charge captures the required rate of return on capital invested by the company. A positive EVA means the company is adding value, while a negative EVA means the company is destroying value.

How is EVM used in project management? ›

Earned value management (EVM) is a project management methodology that integrates schedule, costs, and scope to measure project performance. Based on planned and actual values, EVM predicts the future and enables project managers to adjust accordingly.

What is earned value in agile? ›

Agile earned value management (EVM) is a technique used to measure the performance of an Agile project in relation to three key factors: Cost. Time. Scope.

What is the EV formula? ›

As stated earlier, the formula for EV is essentially the sum of the market value of equity (market capitalization) and the market value of a company's debt, less any cash. A company's market capitalization is calculated by multiplying the share price by the number of outstanding shares.

How do you calculate %EV? ›

To calculate enterprise value, take current shareholder price — for a public company, that's market capitalization. Add outstanding debt and then subtract available cash.

What is EV and how is it calculated? ›

The enterprise value calculation involves subtracting the company's cash or liquid assets (not including stocks or other securities) from the sum of its total debt and market capitalization.

How to measure earned value? ›

Earned value can be computed this way : Eearned Value = Percent complete (actual) x Task Budget. For example, if the actual percent complete is 50% and the task budget is $10,000 then the earned value of the project is $5,000, 50% of the budget provided for this project.

How to create an earned value chart in Excel? ›

Choose View > Table, then choose More Tables. In the list, select Earned Value, Earned Value Cost Indicators, or Earned Value Schedule Indicators. If you're not sure which table, just pick Earned Value. Choose Apply.

How do you calculate value earned? ›

As mentioned earlier here is the formula to calculate the earned value: EV = Percent complete (actual) x Task Budget.

What is the formula for EV? ›

How Do You Calculate Enterprise Value? To calculate market capitalization, multiply the number of outstanding shares by the current stock price. Next, total all debt on the company's balance sheet. Finally, add the market capitalization to the total debt and subtract any cash and cash equivalents from the result.

How to calculate vac? ›

Variance at Completion (VAC) is the difference between the Budget at Completion (BAC) and the Estimate at Completion (EAC) (VAC = BAC - EAC).

Top Articles
Smart TVs: Everything You Need to Know
Understanding Double-Spending and How to Prevent Attacks
English Bulldog Puppies For Sale Under 1000 In Florida
Katie Pavlich Bikini Photos
Gamevault Agent
Pieology Nutrition Calculator Mobile
Hocus Pocus Showtimes Near Harkins Theatres Yuma Palms 14
Hendersonville (Tennessee) – Travel guide at Wikivoyage
Compare the Samsung Galaxy S24 - 256GB - Cobalt Violet vs Apple iPhone 16 Pro - 128GB - Desert Titanium | AT&T
Vardis Olive Garden (Georgioupolis, Kreta) ✈️ inkl. Flug buchen
Craigslist Dog Kennels For Sale
Things To Do In Atlanta Tomorrow Night
Non Sequitur
Crossword Nexus Solver
How To Cut Eelgrass Grounded
Pac Man Deviantart
Alexander Funeral Home Gallatin Obituaries
Energy Healing Conference Utah
Geometry Review Quiz 5 Answer Key
Hobby Stores Near Me Now
Icivics The Electoral Process Answer Key
Allybearloves
Bible Gateway passage: Revelation 3 - New Living Translation
Yisd Home Access Center
Pearson Correlation Coefficient
Home
Shadbase Get Out Of Jail
Gina Wilson Angle Addition Postulate
Celina Powell Lil Meech Video: A Controversial Encounter Shakes Social Media - Video Reddit Trend
Walmart Pharmacy Near Me Open
Marquette Gas Prices
A Christmas Horse - Alison Senxation
Ou Football Brainiacs
Access a Shared Resource | Computing for Arts + Sciences
Vera Bradley Factory Outlet Sunbury Products
Pixel Combat Unblocked
Movies - EPIC Theatres
Cvs Sport Physicals
Mercedes W204 Belt Diagram
Mia Malkova Bio, Net Worth, Age & More - Magzica
'Conan Exiles' 3.0 Guide: How To Unlock Spells And Sorcery
Teenbeautyfitness
Where Can I Cash A Huntington National Bank Check
Topos De Bolos Engraçados
Sand Castle Parents Guide
Gregory (Five Nights at Freddy's)
Grand Valley State University Library Hours
Hello – Cornerstone Chapel
Stoughton Commuter Rail Schedule
Nfsd Web Portal
Selly Medaline
Latest Posts
Article information

Author: Neely Ledner

Last Updated:

Views: 6240

Rating: 4.1 / 5 (62 voted)

Reviews: 85% of readers found this page helpful

Author information

Name: Neely Ledner

Birthday: 1998-06-09

Address: 443 Barrows Terrace, New Jodyberg, CO 57462-5329

Phone: +2433516856029

Job: Central Legal Facilitator

Hobby: Backpacking, Jogging, Magic, Driving, Macrame, Embroidery, Foraging

Introduction: My name is Neely Ledner, I am a bright, determined, beautiful, adventurous, adventurous, spotless, calm person who loves writing and wants to share my knowledge and understanding with you.