What is Earned Value Management? (2024)

Table of Contents
In Practice An Invaluable Tool FAQs

There is a difference between Earned Value (EV) and Earned ValueManagement Systems (EVMS). Earned Value is a performance metric that can be used tomanage any project.

It provides meaningful comparison between planned and completed work and helps to answer the key project control questions:

  1. How much have we completed so far?
  2. Are we on schedule?
  3. Are we within budget?

Or, simply, how well are we doing? By enabling you to answer these questions, EV and EVM become powerful project management tools.

Earned Value Management (EVM) and Earned Value Management systems (EVMS) are management and control criteria and systems thatuse Earned Value as a key performance metric.

Many companies find EVM methodologies and, in particular, all the criteria defined in the ANSI EIA-748 standard to be an administrative burden. However, it is possible toimplement EVM and reap the benefits of the EV metric and its derived indicators without taking on the rigorous cost of the extreme EIA-748 implementation.

In Practice

Earned Value is an objective and reliable productivity measure. It is reliable for both progressso far and prediction as towhen the project is going to finish, and how much it is going to cost. EV also lets you compare performance across any project of anysize. The three pillars for EVM are: scope, budget over time and progress data.

From the schedule, you can determine the Planned Value (PV) – the work scheduled to be completed by a specific date - and compare it to Earned Value (EV), the budget for the amount of work completed.

If the Earned Value is less than the Planned Value, you are behind schedule, and if the Earned Value is greaterthan the Planned Value, you are ahead of schedule. The Earned Value can be compared to the Actual Cost (AC) to determine whetheryou are above or below budget.

An Example from Capital Project Management

We present an example here of a situation which can be better understood through the application of EVM techniques.

As part of a larger capital development project, a civilian airport is facilitating the construction of a new shuttlebus maintenance facility, and the following plan has been laid out:

  • The facility will be built in 12 stages
  • Each stage will have aplanned duration of 3 months, and an investment budget of $1,250,000
  • This will lead to a total cost of $15,000,000, completed over 3 years

However, after the first year, only 3 stages have been completed, instead of the intended 4. The total costat the end of the first year of construction is $5,250,000.

What is Earned Value Management? (1)

EVM Application

We can apply an EVM calculation to this situation, and find the following figures:

Actual Cost(AC) = $5,250,000

Planned Value (PV) = $5,000,000

Earned Value(EV) = $3,750,000

Where AC is the real cost to date, and PVrepresents the cost estimated to have been spent by now, on 4 stages of the project instead of 3. The EVis the expected cost of completing 3 stages of the project. It is clear that we are underperforming and over-spending.

Now it is possible to calculate several key metrics for assessing the health of the project and the performance to date.

What is Earned Value Management? (2)

Here, the disparity between the AC, PV and EVis clear. We can use these 3 values to calculate variance measurements and performance indices.

What is Earned Value Management? (3)

The Cost Variance (CV) (simply the EV– AC) in this example amounts to $1,500,000, whichcan also be expressed as a 29% overrun.

What is Earned Value Management? (4)

The Schedule Variance (SV) (simply the EV-PV):

= $3,750,000 - $5,000,000 = - $1,250,000.

Stages 1-3 are done, but you planned on getting 1-4 done. The schedule variance can also be expressed as stating that you are 25% behind schedule.

Indices

Indices are used to measure performance on a ratio. If you work perfectly to your plan, your index will be 1.0. Above 1.0, means you are doing better than planned, below 1.0 means you are doing worse than planned.

  • Cost Performance Index (CPI): EV/AC, using the numbers above, the CPI

= 3,750,000/5,250,000= 0.71

  • Schedule Performance Index (SPI): EV/PV

= 3,750,000/5,000,000= 0.75

The schedule performance index (SPI) is defined as the Earned Value divided by the Planned Value and is useful for identifying schedule problems, especially when used with critical path information. The CPI and SPI indices can be used to compare performance across projects regardless of their size.

Long-term projections

Earned Value metrics and indices have proven to be a reliable and sound basis for forecasting. Forecasts can be built using the CPI to create an estimate at completion (EAC) which can be compared to the Budget at Complete (BAC) to create at complete variances in real numbers and as a percentage.

What is Earned Value Management? (5)

  • Using the values above the Estimate at Complete (EAC) = AC + (BAC-EV)/CPI

= $5,250,000 + ($15,000,000 - $3,750,000)/0.71 = $21,095,070

  • The Variance at Complete (VAC), or the predicted overrun = EAC-BAC

= $21,095,070 - $15,000,000 = $6,095,070

We can also calculate what effort will be required to get the project back on schedule.

To finish the project to budget:

Performance required to complete is expressed usingthe To Complete Performance Index (TCPI)

= remaining work/ remaining funds ((BAC-EV)/ (BAC-AC))

= ($15,000,000 – $3,750,000)/ ($15,000,000 – $5,250,000) = 1.153

Work would have to be completed at 115.3% the rate originally planned. Compared to the to-date Performance index of 0.71 you may conclude with that this is not likely to happen. Studies on CPI has shown performance tends to stabilise within 10% by the 20 perecent completion point.

Trending

As demonstrated above, cumulative performance indices are useful for predictions and forecasting. Performing EV analyses and Index calculations at timely and regular intervals, such as weekly or monthly, are useful for EVM metric trending. How does our performance vary and what effect does it have on variance calculations and analysis?

Periodic recording and trending allows you to direct attention to the deviations that require attention and ignore minor fluctuations, as well as treating them as early warnings.

An Invaluable Tool

Our example shows how EVM metrics can give insight into valuable information and be used as early warning signals on project health. Reported at regular and timely intervals it allows project managers to make better decisions and take corrective actions early in the project.

Safran Project incorporates a number of project management techniques, including EVM, to help manage large capital projects. For more information on our project scheduling tool, click the linkbelow.

About The Author

Øyvind Røberg

Passionate Product Manager Øyvind has been a member of the Safran team for more than two decades. Prior to joining Safran, Øyvind earned a Bachelor of Science in Mathematics/Petroleum Engineering from the University of Stavanger, and a Masters in Marketing Management from the Norwegian Business School.

What is Earned Value Management? (2024)

FAQs

What is earned value management in simple terms? ›

Earned value management (EVM) is a project management methodology that integrates schedule, costs, and scope to measure project performance.

What is an EVM example? ›

Earned value management example – 1. Let's imagine we are building a wind power plant. The project is set to be completed in 10 months with an estimated cost of $500,000. The project has been running for 5 months now, the team has spent $220,000 and completed an amount of work worth $255,000.

What are the three basic metrics of Earned Value Management? ›

The Essential EVM Metrics You Need to Track

Here are the key metrics you need to focus on: Planned Value (PV): The budgeted cost of the work scheduled to be completed. Earned Value (EV): The value of the work actually completed. Actual Cost (AC): The actual cost incurred for the completed work.

What is the formula for earned value management? ›

To calculate EV, you multiply the percentage of completed work by the original budget allocated to that work. EV allows project managers to assess how much value has been achieved relative to the planned value and helps determine if the project is ahead or behind schedule.

What is earned value for dummies? ›

The definition of earned value management for dummies is that EVM is a way to measure project performance on the basis of: Time - Comparing the amount of work which has been done compared to what was scheduled (are we going to deliver in time?)

What is the 50 50 rule earned value? ›

It assignes 50% of a project's value at the start of the project and delivers the rest at the project's completion. By examining the progress of their initial project phases, they can keep their projects and their spending focused. Earned value is one of three important data points for projects.

Is earned value a KPI? ›

Earned value (EV) is a key performance indicator (KPI) that signifies a quantified value of work accomplished on a project at a given date.

What is the EVM explained? ›

Earned Value Management (EVM) helps project managers to measure project performance. It is a systematic project management process used to find variances in projects based on the comparison of worked performed and work planned.

What is the difference between EV and PV? ›

Current EV is the sum of the budget for the activities accomplished in a given period. Earned Value is also called Budgeted Cost of Work Performed (BCWP). Planned Value (PV) is determined by the cost and schedule baseline. Actual Cost (AC) is determined by the actual cost incurred on the project.

What does a negative etc. indicate? ›

I have checked each negative ETC, and it appears that the system is adjusting the forecast when a cost has incurred and has become actual cost but has not been budgeted. The system seems to assume we have posted too much costs and adjust the forecast by reversing the cost overspent.

What is the earned value rule? ›

It's the relationship between the budget and the percentage of completion of a project. It is a method used to calculate the health and status of any project by taking time and cost into consideration. Earned value can be computed this way : Eearned Value = Percent complete (actual) x Task Budget.

What are the principles of EVM? ›

EVM Principles. At its essence, Earned Value is a measure of project performance comparing work completed against work planned, as of a given date. It is used to (1) measure, (2) forecast, and (3) improve project performance for an organization.

What best defines earned value? ›

This method relies on a key measure known as the project's earned value. Oftentimes the term “earned value” is defined as the “budgeted cost of worked performed” or BCWP.

How is EVM calculated? ›

Earned value management formulas
Formula NameFormula
Schedule Performance IndexSPI = EV / PV
Estimate At CompletionEAC = BAC / CPI
Estimate To CompletionETC = EAC – AC
To-Complete Performance Index (BAC)TCPI = (BAC-EV) / (BAC-AC)
7 more rows

Top Articles
Ile kosztuje kilowatogodzina prądu w 2024?
Darmowe kryptowaluty i Bitcoiny - jak zdobyć (+bez depozytu)
Encore Atlanta Cheer Competition
Top 11 Best Bloxburg House Ideas in Roblox - NeuralGamer
Design215 Word Pattern Finder
Odawa Hypixel
Booknet.com Contract Marriage 2
Ymca Sammamish Class Schedule
How Many Cc's Is A 96 Cubic Inch Engine
THE 10 BEST Women's Retreats in Germany for September 2024
Displays settings on Mac
Big Y Digital Coupon App
Milk And Mocha GIFs | GIFDB.com
Space Engineers Projector Orientation
Shariraye Update
123Moviescloud
Ree Marie Centerfold
Socket Exception Dunkin
Kaomoji Border
Craiglist Galveston
065106619
London Ups Store
Second Chance Maryland Lottery
Https Paperlesspay Talx Com Boydgaming
Qhc Learning
Rochester Ny Missed Connections
Conscious Cloud Dispensary Photos
Sound Of Freedom Showtimes Near Movie Tavern Brookfield Square
Democrat And Chronicle Obituaries For This Week
Pokémon Unbound Starters
Darknet Opsec Bible 2022
Nikki Catsouras: The Tragic Story Behind The Face And Body Images
Street Fighter 6 Nexus
Gasbuddy Lenoir Nc
Sports Clips Flowood Ms
RUB MASSAGE AUSTIN
Laurin Funeral Home | Buried In Work
Whitehall Preparatory And Fitness Academy Calendar
Natashas Bedroom - Slave Commands
20 Best Things to Do in Thousand Oaks, CA - Travel Lens
Craigslist Ludington Michigan
Download Diablo 2 From Blizzard
Panorama Charter Portal
2132815089
Best GoMovies Alternatives
Unlock The Secrets Of "Skip The Game" Greensboro North Carolina
Southwest Airlines Departures Atlanta
Whitney Wisconsin 2022
City Of Irving Tx Jail In-Custody List
Lightfoot 247
Best brow shaping and sculpting specialists near me in Toronto | Fresha
What Are Routing Numbers And How Do You Find Them? | MoneyTransfers.com
Latest Posts
Article information

Author: Trent Wehner

Last Updated:

Views: 5764

Rating: 4.6 / 5 (76 voted)

Reviews: 83% of readers found this page helpful

Author information

Name: Trent Wehner

Birthday: 1993-03-14

Address: 872 Kevin Squares, New Codyville, AK 01785-0416

Phone: +18698800304764

Job: Senior Farming Developer

Hobby: Paintball, Calligraphy, Hunting, Flying disc, Lapidary, Rafting, Inline skating

Introduction: My name is Trent Wehner, I am a talented, brainy, zealous, light, funny, gleaming, attractive person who loves writing and wants to share my knowledge and understanding with you.