Earned value analysis, for the rest of us (2024)

Earned value is a powerful tracking and budgeting feature in Project. Despite the slew of intimidating acronyms that defines it (like AC, BCWP, TPI, EV, and the like), it isn’t especially complicated. Earned value helps you answer questions like, “Looking at the amount of work done so far in this project, how much money were we supposed to have spent?” Which then leads to other questions like, "Will we finish on time?"

A simple example You’re working on a gardening project for 10 homes in a cul-de-sac, and you expect to get the entire project of 10 homes done in 10 months. Further, you need to complete one home’s garden in each month. Let’s walk through some of the details on this project.

  • $10,000 is your total budget for all 10 homes.

  • $1,000 is budgeted for each home, which means you plan to spend $1,000 per month on the entire project. This includes money spent on plants, tools, and a gardener.

  • You ask your account for a report after 2 months have passed. The accountant tells you $1,500 has been spent on the project so far. You think, “Great, I’m saving money.”

  • Then you realize your mistake. After 2 months’ time, 20 percent of the project should have been done, because 2 months is 20 percent of the 10 months that you had originally planned to spend on the project. But only one and a half gardens are actually done, not 2.

  • So, after two months, you should have spent 20 percent X $10,000 (or $2,000) on the project to get it done on time, and two gardens should be complete—not $1,500 for one and half gardens. Now you realize you’re actually behind schedule. Yikes! Time to have a talk with the gardener.

Here’s the tricky thing (and great thing) about earned value. It marries time with money because it multiplies currency by scheduled time (or percent complete, in the jargon of professional project managers).

The lesson? “Time is money,” as the old saying goes. Now, you can’t boast your prowess with earned value quite yet. You need to read on . . .

More on earned value

Display earned value

Project displays earned value information two ways: with views and with reports. But first you need to do a few things to set up earned value for reporting.

Using reports

  1. Choose Project > Reports > More Reports.

  2. Choose Costs, and then choose Earned Value.

Using views

  1. Choose View > Table, then choose More Tables.
    Earned value analysis, for the rest of us (1)

  2. In the list, select Earned Value, Earned Value Cost Indicators, or Earned Value Schedule Indicators.
    If you’re not sure which table, just pick Earned Value.

  3. Choose Apply.

Top of Page

Interpret earned value

Three key values are at the root of earned value analysis, and you pretty much need to know at least these three values to use earned value.

Planned value (PV) This also known by the acronym BCWS.

This is the budgeted (or baseline) cost of tasks estimated at the start the project plan, based on the costs of resources assigned to those tasks, plus any fixed costs associated with the tasks, up to the status date you choose.

For example, the total planned budget for a 4-day task is $100 and it starts on a Monday. If you set the status date to the following Wednesday, you’ll see that the PV is $75. However, with this value, you don’t know how well your project is doing.

Actual Cost (AC) This is also known by ACWP.

This is the actual cost required to complete all or some portion of the tasks, up to the status date. For example, if the 4-day task actually incurs a total cost of $35 during each of the first 2days, the AC for this period is $70 (but the PV is still $75).

However, with this value, you don’t know how well your project is doing. For example, if you planned to get a lot more work done for that same $70, that doesn’t sound good. You need to know (you guess it) earned value to fully assess the efficiency of your project.

Earned Value (EV) This is also known as BCWP

This is the value of the work performed by the status date, measured in currency.

For example, if after 2days 60%percent of the work on a task has been completed, you might expect to have spent 60percent of the total task budget, or $60. If it turns out that you spent $80, then you can safely say you’re over budget and behind schedule. Ouch!

An important theme running through these common earned value terms is the status date. Earned value analysis assumes you want to see the progress on your project prior to a specific point in time that you choose.

Because a picture is worth a thousand words, let’s look at this graphically. Here’s a chart showing a steady accumulation of cost over the lifetime of a project. The dotted line shows a steady expenditure over the lifetime of the project.

Earned value analysis, for the rest of us (2)

After work on the project has begun, a chart of the key values of earned value analysis may look like this.

Earned value analysis, for the rest of us (3)

The status date determines the values Project calculates. The actual cost (AC) of this project has exceeded the budgeted cost. The earned value (EV) reflects the true value of the work performed. In this case, the value of the work performed is less than the amount spent to perform that work.

Top of Page

Some advice on using earned value

Do this

How

Take action soon

The earlier in a project's life cycle you identify such discrepancies between actuals costs, budgeted costs, and earned value the sooner you can take steps to remedy the problem.

Work harder

Easier said than done. The more work you get done before the next status date for determining earned value, the better. Simply hiring more workers may not help, but hiring cheaper workers might. Or you may need to “walk the floor,” to find out why workers aren’t being more productive. Or maybe the problem is with the managers who are providing machinery that needs more maintenance than expected. There could be many reasons, but the point is, using a “numbers approach” with earned value will help you spot negative trends.

Work smarter

Don’t chase after productivity problems on those tasks that are less important than others. Check tasks on the critical path first for the greatest impact on positive earned value numbers.

Re-run your reports

An earned value analysis at the end of a project really has little value. The sources of your project’s problems is likely early in it, and will likely have had too much impact to correct without incurring great cost and frustration from your team, manager, and other stakeholders. Get in the habit of running earned value reports monthly, if you’re going to do them at all.

Don’t sweat the early stuff

If you see problems very early in the project, it could just be ramp-up costs, or the costs of training, getting everyone on-board, abundant but necessary early collaboration with your team, and other housekeeping chores. Don’t ignore these early signs of trouble, but they may be more understandable early in the project than later.

Further reading

  • Track the progress of your schedule, from simple to expert

  • Specify the earned value method for percent complete

  • How Project schedules tasks: Behind the scenes

Earned value analysis, for the rest of us (2024)

FAQs

What is EVM for the rest of us? ›

The concept that we call “Earned Value Management for the Rest of Us” (EVM FRU) focuses on those principles and reduces EVM to the minimum requirements needed to track and measure project performance for an organization.

What is the Earned Value Analysis? ›

What is Earned Value Analysis? Earned Value Analysis (EVA) is a method that allows the project manager to measure the amount of work actually performed on a project beyond the basic review of cost and schedule reports. EVA provides a method that permits the project to be measured by progress achieved.

What is Earned Value Analysis quizlet? ›

A measure of progress which may be expressed in cost or labour hours. Earned Value Analysis. "The analysis of project progress where the actual money, hours (or other measures) budgeted and spent is compared to the value of work achieved.

What is Earned Value Analysis PDF? ›

Earned Value is a well-known project management tool that uses information on cost, schedule and work performance to establish the current status of the project. By means of a few simple rates, it allows the manager to extrapolate current trends to predict their likely final effect.

Why is it difficult to use EVM? ›

Without the necessary level of detail in collecting planned and actual expenses, Earned Value Management effectiveness becomes severely compromised. The AATT Project found that the level of information gained did not justify the workload placed on the task leads and/or PIs or the AATT Systems Management staff.

Is EVM worth the effort? ›

Without EVM, you may think your project is running smoothly, only to realize later that you've burned through most of your budget or the work isn't meeting expectations. One advantage of earned value management is that it helps you catch these issues early so you can correct them before they spiral out of control.

What is the EVM explained? ›

Earned Value Management offers invaluable insights into project performance, cost control, and schedule management. By integrating project scope, schedule, and cost data, EVM allows project managers to assess progress, forecast future performance, and make informed decisions to keep projects on track.

What are the two important elements in earned value analysis? ›

Key Components in Earned Value Analysis

Planned Cost/Planned Value (PC or PV): This represents the estimated cost of the work scheduled to be completed by a certain date. It sets the baseline against which actual progress is measured. Earned Value (EV): This represents the value of work actually completed to date.

What are the three Earned Value Analysis Formulae? ›

Earned Value Calculations
• Cost Variance: CV = EV – AC• Cost Performance Index: CPI = EV/AC
• Schedule Variance: SV = EV – PV• Schedule Performance Index: SPI = EV/PV

What is earned value for dummies? ›

The definition of earned value management for dummies is that EVM is a way to measure project performance on the basis of: Time - Comparing the amount of work which has been done compared to what was scheduled (are we going to deliver in time?)

What does Earned Value Analysis help in the consideration of? ›

The definition of Earned Value Analysis according to the PMBOK is: “Earned value analysis compares a performance measurement baseline to the actual schedule and cost performance. It integrates scope baseline with the cost baseline and schedule baseline to form the performance measurement baseline.

What does an earned value Analyst do? ›

Works with Program Management, IPTs, CAMs, and functional business analysts to perform detailed cost/schedule planning, Earned Value variance analysis, identification of cost/schedule problems, and developing corrective action plans. Timely and accurate Estimate at Completion development, analysis, and reporting.

What is Earned Value Analysis What is the purpose of variance analysis? ›

Variance Analysis is essential for measuring the difference between planned and actual project performance, highlighting areas that require attention. Earned Value Management (EVM) is a robust method that integrates scope, cost, and schedule metrics to assess project progress and predict future performance.

What are the metrics for Earned Value Analysis? ›

The earned value metric is actually the planned value of the work that has been accomplished, but it is often referred to as the budgeted cost for work performed (BCWP). The baseline plan that performance is measured against is an aggregation of the timephased value of the work planned to be performed.

What are the Earned Value Analysis variables? ›

It contains three lines: Planned Value (PV), Earned Value (EV), and Actual Value (AV). Earned Value (EV) shows the cumulative value of the planned work that has already been completed over time (costs or effort). Actual Value (AV) shows the accumulated value of the actual costs incurred or costs at a given time.

What is EVM standard for? ›

EVM helps you clearly and objectively see where your project is headed compared to where it is supposed to be. The Standard for Earned Value Management is intended for any practitioner or organization who wants to expand their toolset and use EVM to improve project performance.

What is the difference between EVM and EVMS? ›

Based on planned and actual values, EVM predicts the future and enables project managers to adjust accordingly. In turn, Earned Value Management Systems (EVMS) refer to the software, processes, tools, and templates used for EVM. Another important terminology used in this context is earned value analysis (EVA).

What exactly is EVM? ›

What is the Ethereum Virtual Machine (EVM)? The Ethereum Virtual Machine (EVM) is a decentralized computation engine that executes smart contracts on the Ethereum network. It is a crucial component of Ethereum's infrastructure, enabling the execution of code exactly as intended.

When should EVM be used? ›

It is normally used in conjunction with cost plus and fixed-price incentive contracts with discrete work scope. The purpose of EVM is to ensure sound planning and resourcing of all tasks required for contract performance.

Top Articles
What is Lynch's rule of 20? | Peter Lynch rule of 20
How to make a file private  |  Google Workspace Knowledge Center
Vaya Timeclock
Us 25 Yard Sale Map
Tyrunt
How To Get Free Credits On Smartjailmail
Craigslist Dog Sitter
Palace Pizza Joplin
Steve Strange - From Punk To New Romantic
Hover Racer Drive Watchdocumentaries
Pwc Transparency Report
Turning the System On or Off
Spartanburg County Detention Facility - Annex I
Jackson Stevens Global
Teenleaks Discord
Napa Autocare Locator
Watch The Lovely Bones Online Free 123Movies
H12 Weidian
Veracross Login Bishop Lynch
Vegas7Games.com
Busted Mcpherson Newspaper
Amazing Lash Studio Casa Linda
Craigslist St. Cloud Minnesota
Craigslist Roseburg Oregon Free Stuff
How to Watch Every NFL Football Game on a Streaming Service
Foodsmart Jonesboro Ar Weekly Ad
Astro Seek Asteroid Chart
Possum Exam Fallout 76
24 Hour Drive Thru Car Wash Near Me
Craigslist Texas Killeen
Napa Autocare Locator
35 Boba Tea & Rolled Ice Cream Of Wesley Chapel
Rust Belt Revival Auctions
How to Play the G Chord on Guitar: A Comprehensive Guide - Breakthrough Guitar | Online Guitar Lessons
Colorado Parks And Wildlife Reissue List
Gold Nugget at the Golden Nugget
Frcp 47
Wait List Texas Roadhouse
About My Father Showtimes Near Amc Rockford 16
Executive Lounge - Alle Informationen zu der Lounge | reisetopia Basics
Stranahan Theater Dress Code
Craigslist Rooms For Rent In San Fernando Valley
Reilly Auto Parts Store Hours
R/Gnv
8 4 Study Guide And Intervention Trigonometry
Christie Ileto Wedding
Craigslist Sarasota Free Stuff
Unit 4 + 2 - Concrete and Clay: The Complete Recordings 1964-1969 - Album Review
Deviantart Rwby
Inside the Bestselling Medical Mystery 'Hidden Valley Road'
Latest Posts
Article information

Author: Errol Quitzon

Last Updated:

Views: 5334

Rating: 4.9 / 5 (79 voted)

Reviews: 94% of readers found this page helpful

Author information

Name: Errol Quitzon

Birthday: 1993-04-02

Address: 70604 Haley Lane, Port Weldonside, TN 99233-0942

Phone: +9665282866296

Job: Product Retail Agent

Hobby: Computer programming, Horseback riding, Hooping, Dance, Ice skating, Backpacking, Rafting

Introduction: My name is Errol Quitzon, I am a fair, cute, fancy, clean, attractive, sparkling, kind person who loves writing and wants to share my knowledge and understanding with you.