EVM Metrics: Here's what to know about critical EVM metrics (2024)

What are the most important EVM metrics?

EVM metrics (metrics for earned value management) are the metrics which project managers and companies use to determine the earned value of their projects as they are being conducted, so that they can gauge performance and ultimately deliver on time and on budget.

All EVM metrics are important because they combine to give a more comprehensive overview of project health than traditional accounting oriented measures which track projects one dimensionally, like how many dollars have we spent vs. what was budgeted.

In contract to this, EVM metrics give project managers and teams tighter and more reliable controls over cost (budget) and time (schedule) which means better decisions can be made and projects can be better controlled.

The three main and critical EVM metrics are planned value, actual cost and earned value.

Earned value is the core EVM metric, but it leans on and requires the other two metrics of planned value (PV) and actual cost (AC) are given context and meaning.

Here are some short explanations of the three key EVM metrics:

Planned value (PV):

This EVM metric is calculated at the beginning of a project, and is the total planned value or total project budget. For example, if a project budget to build a road is $1,000,000, then the total planned value of the project is $1,000,000.

Planned value sets the baseline for schedule performance, meaning if we stay on track with the planned value, we are on course to deliver the project on time.

Actual cost (AC):

This EVM metric is exactly what it sounds like; it's the actual costs incurred on the project so far. If a project has been running for 3 months and cost $200,000, then the actual costs are naturally $200,000.

Earned value (EV):

Earned value, the key EVM metric, enables a project manager to see the amount of value which has been earned or generated on the project so far. For example, a project which is 50% complete and has a budget at completion (BAC) of $1,000,000 will have an earned value of %500,000.

You can read more about the earned value formula here.

How to use these EVM metrics properly

Unlike some other more straightforward metrics, EVM metrics require a deeper comparison and analysis against each other - and against the more peripheral but also important EVM metrics.

Once you have found or calculated your core EVM metrics, you'll want to pull in the other metrics including schedule variance, cost variance and estimate at completion.

These other metrics give context to our base metrics. For example, the cost variance compares our earned value to the actual cost of the project so far so we understand whether we have spent more or less than we should have to reach this amount of earned value. In other words, did we spend the right amount of money to produce this amount of input.

Schedule variance is an EVM metric which does the same thing for the planned value. By subtracting our planned value from our earned value (here's more EVM formulas) we can see whether or not we are ahead of or behind schedule right now.

We can also use our earned value metrics to better forecast what the project is likely to look like at the end now that we have more real-world information and data which has been collected during some prior period of the project.

Instead of forecasting and projecting based on theory, we can use the data we have and these EVM metrics to make more accurate projections - and then adjust our strategies based on these projections.

You will need a comprehensive understanding of all of the EVM metrics to build a complete picture of the current situation.

How to track EVM metrics

Companies work really hard to track their KPI's and key metrics. As is the case with most important business metrics, there are a few ways to approach documenting, tracking and 'scoring' these metrics.

Many of the methods still used today are largely manual, with companies tracking their EVM metrics using spreadsheets and pieces of paper. This has worked for many years, but it also requires a lot of manual data entry and results in slower data movement and slower decision making.

Luckily, the rise of cloud-based project management softwares (like this construction software) have eliminated many of the inputs which slowed down our information management. Instead of project managers having to wait for field and site level data in the form of paper, word docs and PDFs to feed in from site, they can now reconcile and display all of this data in real-time.

Workers are now using mobile and tablets to document work, which means that digital data can move instantly into the project managers domain.

Once here, many modern systems can aggregate all of this data and display it in tracking charts, dashboards and EVM metrics scores.

This evolution in data capture and movement is bringing a new level of power to earned value management. EVM metrics always had the promise of real-time project decisions, and technology is making that a reality today.

EVM Metrics: Here's what to know about critical EVM metrics (2024)

FAQs

EVM Metrics: Here's what to know about critical EVM metrics? ›

EVM is built on three metrics: Planned value, earned value, and actual cost. Think of these metrics in terms of your project budget and schedule. Planned value represents how you expect to earn your project budget over the duration of the project.

What is the most critical EVM metric? ›

The three main and critical EVM metrics are planned value, actual cost and earned value. Earned value is the core EVM metric, but it leans on and requires the other two metrics of planned value (PV) and actual cost (AC) are given context and meaning.

What is the critical ratio in EVM? ›

Critical Ratio (CR): This indicator combines both the cost performance index (CPI) and schedule performance index (SPI) to represent the project status. This indicator takes care of cost and schedule trade-offs. CR = 1 means project performance is on target. What are the limitations of EVM indexes?

How are EVM metrics used? ›

EVM metrics are the key performance indicators that provide insights into a project's cost and schedule performance. These metrics allow project managers to measure and analyze the variance between planned, earned, and actual values.

What is EVM performance measures? ›

Earned Value: Metrics and Performance Measurements

Earned value performance measurements look at the project cost and. schedule performance by analyzing the cost and schedule variance along. with cost and schedule efficiency. The formulas used are as follows: Variance Analyses.

What are the three key EVM metrics? ›

EVM is built on three metrics: Planned value, earned value, and actual cost. Think of these metrics in terms of your project budget and schedule. Planned value represents how you expect to earn your project budget over the duration of the project.

What are the three basic metrics of earned value management? ›

Comprised of planned value (PV), earned value (EV), and actual cost (AC), it lets you accurately compare performance across any project of any size.

How is EVM calculated? ›

EV = BAC * Actual % Complete, where BAC is the Budget at Completion, and Actual % Complete is the percentage of actual work completed up to the current reporting period.

What is the 50 50 rule in EVM? ›

50/50 RULE – A task is considered 50% complete when it starts. The remaining 50% credit is given when the task is completed.

What factors affect EVM? ›

EVM solely focuses on the project schedule (SPI) and value (CPI), and doesn't address alternative vital aspects of quality, Risk, safety and social factors.

What role do EVM metrics play in agile? ›

Agile Projects and EVM

EVM methods stress the importance of establishing a measurement baseline before the project starts. From this baseline of time and budgetary values, actual hours, costs, and technical progress are compared for the duration of the project.

What are the two metrics where EVM is used for monitoring? ›

Using the most recent terminology, EVM consists of three metrics named Planned Value (PV), Actual Cost (AC) and Earned Value (EV). PV represents the planned cumulative expenditure as the project progresses, that is, the planned cumulative cost.

What is needed to establish EVM parameters? ›

Once you have the foundations of your EVA completed, you need to establish the following three areas: Planned Value (what was the budget you planned for?) Actual Cost (what has your project cost to date?) Earned Value (what has your project earned or accomplished so far?)

What is an EVM example? ›

Earned value management example – 1. Let's imagine we are building a wind power plant. The project is set to be completed in 10 months with an estimated cost of $500,000. The project has been running for 5 months now, the team has spent $220,000 and completed an amount of work worth $255,000.

Does EVM measure quality? ›

It compares the planned scope, schedule, and cost of a project with the actual work done and the value delivered. However, EVM does not directly account for the quality of the software product or the customer satisfaction.

What are the components of EVM? ›

The EVM consists of Control Unit (CU) and Ballot Unit (BU) and their connection cables. 2. The CU is kept with the Presiding Officer while BU and VVPAT are kept in the voting compartment.

Which EVM performance measurement metric tells you what will be the forecasted total cost of the project at completion? ›

CPI can be used to forecast your project's completion. For example, you can divide your total project budget by your current CPI to get the expected total cost at completion.

Top Articles
Did You Know God Wants You To Be Rich? - Dominion TV
Discipline in the Montessori Classroom | Mansio Montessori
Where are the Best Boxing Gyms in the UK? - JD Sports
Cottonwood Vet Ottawa Ks
Summit County Juvenile Court
FFXIV Immortal Flames Hunting Log Guide
Math Playground Protractor
Co Parts Mn
30% OFF Jellycat Promo Code - September 2024 (*NEW*)
Back to basics: Understanding the carburetor and fixing it yourself - Hagerty Media
Autozone Locations Near Me
Guardians Of The Galaxy Vol 3 Full Movie 123Movies
Ladyva Is She Married
The Binding of Isaac
Chicken Coop Havelock Nc
Crossword Nexus Solver
Vanessa West Tripod Jeffrey Dahmer
Mani Pedi Walk Ins Near Me
Wisconsin Women's Volleyball Team Leaked Pictures
Invert Clipping Mask Illustrator
Weve Got You Surrounded Meme
Reser Funeral Home Obituaries
104 Presidential Ct Lafayette La 70503
Craigslist Lake Charles
Restored Republic June 16 2023
Spectrum Outage in Queens, New York
Pulitzer And Tony Winning Play About A Mathematical Genius Crossword
Craigslist Comes Clean: No More 'Adult Services,' Ever
Gopher Hockey Forum
Osrs Important Letter
Kacey King Ranch
Transformers Movie Wiki
Ofw Pinoy Channel Su
Tmj4 Weather Milwaukee
Craigslist Central Il
Prima Healthcare Columbiana Ohio
The Blackening Showtimes Near Regal Edwards Santa Maria & Rpx
Sabrina Scharf Net Worth
301 Priest Dr, KILLEEN, TX 76541 - HAR.com
Tyler Perry Marriage Counselor Play 123Movies
Panorama Charter Portal
Lcwc 911 Live Incident List Live Status
Noaa Duluth Mn
The Realreal Temporary Closure
6576771660
Craigslist Woodward
Enr 2100
Dietary Extras Given Crossword Clue
Santa Ana Immigration Court Webex
Game Akin To Bingo Nyt
Ubg98.Github.io Unblocked
Bunbrat
Latest Posts
Article information

Author: Kimberely Baumbach CPA

Last Updated:

Views: 5390

Rating: 4 / 5 (41 voted)

Reviews: 80% of readers found this page helpful

Author information

Name: Kimberely Baumbach CPA

Birthday: 1996-01-14

Address: 8381 Boyce Course, Imeldachester, ND 74681

Phone: +3571286597580

Job: Product Banking Analyst

Hobby: Cosplaying, Inline skating, Amateur radio, Baton twirling, Mountaineering, Flying, Archery

Introduction: My name is Kimberely Baumbach CPA, I am a gorgeous, bright, charming, encouraging, zealous, lively, good person who loves writing and wants to share my knowledge and understanding with you.