Replacing Resources in Microsoft Project | PPM Works Blog (2024)

Skip to content
Replacing Resources in Microsoft Project | PPM Works Blog (1)Replacing Resources in Microsoft Project | PPM Works Blog (2)

We have had a few different customers recently ask the PPM Works Team how to replace resources on tasks in Microsoft Project. Let’s assume you are using an Enterprise Resource Pool connect via Project Online or Project Server.

Replacing Resources in Microsoft Project | PPM Works Blog (3)

If the new resource is not on the project team you can easily replace the existing resource with the new resource. From the Resource ribbon select Add Resources

Build Team from Enterprise. Select the resource that requires a replacement on the right side and the new resource on the left side and click Replace. Click Ok to save your changes. Project will not replace resources on tasks that are 100% complete and it will only assign the remaining work to the new resource.

Replacing Resources in Microsoft Project | PPM Works Blog (4)

If the resource is already on the project team and has current assignments:

  1. Navigate to a Gantt Chart view.
  2. From the Resource ribbon select Assign Resources.
  3. Use Shift + Click or Control + Click to select multiple tasks.
  4. Click Replace and select the new resource in the Replace Resource dialog box and click OK

Replacing Resources in Microsoft Project | PPM Works Blog (5)

Note: In my example above Selena has replaced Laura on the selected tasks. Laura’s name remains with the task because there was actual work performed on the task prior to replacing her with Selena. Remember, Project will only reassign the remaining work left on the task to the new resource.

Replacing Resources in Microsoft Project | PPM Works Blog (6)

Hope this helps! Please contact us with questions.

Share This Story, Choose Your Platform!

About the Author: Laura Crawford

Related Posts

Page load link
Replacing Resources in Microsoft Project | PPM Works Blog (2024)

FAQs

Replacing Resources in Microsoft Project | PPM Works Blog? ›

In the Assign Resources dialog, in the Resource Name column, select the resource that you want to replace. Choose Replace. In the Replace Resource dialog box, select the resource that you want to replace, and then choose OK.

How to replace resources in MS Project? ›

In the Assign Resources dialog, in the Resource Name column, select the resource that you want to replace. Choose Replace. In the Replace Resource dialog box, select the resource that you want to replace, and then choose OK.

How to fix over allocated resources in MS Project? ›

Overallocation can be solved by the Project Manager by moving the involved tasks to new dates (by setting new start dates or by linking tasks) or by changing resource assignments.

How do I update resources in a project? ›

To replace an existing resource with an enterprise resource, in the Project Resource column, select the resource or generic resource that you want to replace. Under Enterprise Resource, select the new enterprise resource, and then choose Replace.

How do I change resource cost in Microsoft Project? ›

Double-click the resource to open the Resource Information dialog box, and then click the Costs tab. Under Cost rate tables, click the A (Default) tab, and then type a cost value in the Per Use Cost column. In the next row, type a value or percentage change from the previous cost in the Per Use Cost column.

How do you find and replace in MPP? ›

1. Go to menu Task - Find - Replace. 2. In the Replace dialog box select the desired information and click Replace, Replace All or Find Next.

What are the three types of resources in MS Project? ›

In Microsoft Project resources can be anything required to perform tasks – people, equipment, facilities, materials, and even costs. These are categorised into three main resource types: work, materials and costs.

How do I update a project in Microsoft project? ›

On the Project tab, in the Status, group, choose Update Project. In the Update Project dialog box, choose Update work as complete through, and then type or select the date through which you want progress updated. Select Set 0% - 100% complete. If you are updating specific tasks, select Selected Tasks.

How do you update resource availability in MS project? ›

Click View > Resource Views > Resource Sheet. Right-click the resource and choose Information. On the General tab, under Resource Availability, set the dates for when the resource has limited availability, and then set a percent of the resource's time that will be available for your project (Units). Click OK.

How do I replace MS project? ›

16 Best Microsoft Project Alternatives
  1. ClickUp.
  2. Asana.
  3. ProofHub.
  4. Paymo.
  5. Monday.com.
  6. Hitask.
  7. nTask.
  8. Zenkit.
Feb 21, 2024

How do you balance resources in Microsoft Project? ›

Choose Level Resource, and then select the resource to whom tasks are assigned. Use CTRL to select multiple resources. If the selected resource is working on tasks that have multiple resources, the other assignments will not get moved. Level All Use this to level all resources in all tasks within the project plan.

How do you update resource availability in MS Project? ›

Click View > Resource Views > Resource Sheet. Right-click the resource and choose Information. On the General tab, under Resource Availability, set the dates for when the resource has limited availability, and then set a percent of the resource's time that will be available for your project (Units). Click OK.

How do I allocate resources in MS Project? ›

Go to the “Gantt Chart” view, double-click on a task to open the “Task Information” dialog box. After that, go to the “Resources” tab, and select the resources you want to assign to the task. Wrapping up with resource allocation, review your project plan to ensure they are assigned efficiently.

How do you remove resources from a list in Microsoft Project? ›

To delete a resource, on the View menu click Resource Sheet – select the resource's name or select the row that corresponds to the resource – press the Delete key or use the Delete option under the Team tab or right click on the resource's ID and select Delete Resource.

Top Articles
De hypotheek van Financial Chipmunk
Voordelige vliegvakantie met kids - De Budgetman.nl
Po Box 7250 Sioux Falls Sd
The Largest Banks - ​​How to Transfer Money With Only Card Number and CVV (2024)
Uca Cheerleading Nationals 2023
Brady Hughes Justified
Occupational therapist
Jesus Calling December 1 2022
Activities and Experiments to Explore Photosynthesis in the Classroom - Project Learning Tree
Pickswise the Free Sports Handicapping Service 2023
Jcpenney At Home Associate Kiosk
Top Hat Trailer Wiring Diagram
Goldsboro Daily News Obituaries
Craigslist Jobs Phoenix
New Mexico Craigslist Cars And Trucks - By Owner
Thotsbook Com
Sivir Urf Runes
Teenleaks Discord
Unit 33 Quiz Listening Comprehension
Inside the life of 17-year-old Charli D'Amelio, the most popular TikTok star in the world who now has her own TV show and clothing line
Lowes Undermount Kitchen Sinks
Scout Shop Massapequa
Busted Mcpherson Newspaper
Employee Health Upmc
Www.paystubportal.com/7-11 Login
Elbert County Swap Shop
Shoe Station Store Locator
What Sells at Flea Markets: 20 Profitable Items
Unity Webgl Car Tag
Keshi with Mac Ayres and Starfall (Rescheduled from 11/1/2024) (POSTPONED) Tickets Thu, Nov 1, 2029 8:00 pm at Pechanga Arena - San Diego in San Diego, CA
Restored Republic
Club Keno Drawings
Que Si Que Si Que No Que No Lyrics
47 Orchid Varieties: Different Types of Orchids (With Pictures)
Bus Dublin : guide complet, tarifs et infos pratiques en 2024 !
Gwu Apps
Craigslist Georgia Homes For Sale By Owner
Myanswers Com Abc Resources
Pokemon Reborn Locations
Wo ein Pfand ist, ist auch Einweg
3 Zodiac Signs Whose Wishes Come True After The Pisces Moon On September 16
Mbfs Com Login
Here's Everything You Need to Know About Baby Ariel
Csgold Uva
RubberDucks Front Office
This Doctor Was Vilified After Contracting Ebola. Now He Sees History Repeating Itself With Coronavirus
Ups Customer Center Locations
Barback Salary in 2024: Comprehensive Guide | OysterLink
Inside the Bestselling Medical Mystery 'Hidden Valley Road'
Craigslist Farm And Garden Missoula
Wayward Carbuncle Location
Latest Posts
Article information

Author: Stevie Stamm

Last Updated:

Views: 5618

Rating: 5 / 5 (80 voted)

Reviews: 87% of readers found this page helpful

Author information

Name: Stevie Stamm

Birthday: 1996-06-22

Address: Apt. 419 4200 Sipes Estate, East Delmerview, WY 05617

Phone: +342332224300

Job: Future Advertising Analyst

Hobby: Leather crafting, Puzzles, Leather crafting, scrapbook, Urban exploration, Cabaret, Skateboarding

Introduction: My name is Stevie Stamm, I am a colorful, sparkling, splendid, vast, open, hilarious, tender person who loves writing and wants to share my knowledge and understanding with you.