PERT Method - Program Evaluation and Review Technique Example & Definition (2024)

Project managers often use graphical representation tools to understand their projects’ performance. CPM, Gantt, and PERT Charts are used to demonstrate workflow and sequence of activities. Although both scheduling tools serve the same purpose, they are different from each other. In this article, we will discuss the PERT definition and demonstrate how to use PERT Method with the help of an example.

Table of Contents

PERT VS CPM

The PERT Method (orProgram Evaluation and Review Technique) is one of the most common scheduling techniques for network analysis which is used to track and coordinate complex tasks in a project. Similar to the CPM Method, PERT helps to analyze the project work schedule by focusing on each task and calculating the minimum time required to complete the project.

Although both of them use a common approach for preparing the network and determining its critical path, PERT focuses on probabilistic elements for task duration estimation, while CPM deals with low uncertainty in task durations.

What is the PERT defınıtıon? (Program Evaluation and Review Technique)

PERT Method (Program Evaluation and Review Technique) was first developed by the US Navy SPO (Special Projects Office) in 1967 during the Polaris missile development program then it was applied to the other industries. Both CPM and PERT are complementary tools and they are developed at roughly the same time.

Unlike other methods, PERT is an event-oriented technique that uses three-time estimates (optimistic, expected, and pessimistic) for each task. With this aspect, it employs uncertainty while calculating the task durations. These characteristics make the Program Evaluation and Review Technique useful for large-scale, complex, and non-routine projects.

The WBS (Work Breakdown Structure) concept which divides the scope into manageable sections was developed in conjunction with PERT .

Why Would You Use a PERT Chart?

One of the most important responsibilities of a project manager is making correct estimations. Since projects are full of uncertainties, it is often difficult for a project manager to foresee what will happen tomorrow. Besides, project sponsors and key project stakeholders never like uncertainty regarding project costs and milestone dates.

The project manager’s role and responsibilities include reducing and mitigating negative project risks as well as increasing the possibility of opportunities.

Project managers should use PERT charts in conjunction with other tools and techniques if they need more accurate and forecasts. Because PERT Chart employs three time estimations to provide you an averageresult.

PERT Method - Program Evaluation and Review Technique Example & Definition (1)

Key Differences Between the PERT and cpm Method

Below are some key differences between the PERT and CPM Method (Critical Path Method)

  • In the Critical Path Method activity durations are well defined but in PERT, time estimations are uncertain.
  • The Critical Path Method is a method of control of time and costs, however, PERT is a technique of planning and control of time.
  • There are three estimates in PERT such as optimistic, pessimistic, and most likely. In the Critical Path Method, there is only one estimate.
  • In PERT Chart, only FS relationship type is applicable. In CPM Chart 4 relationship types (FS,SS,SF,FF) can be applicable.
  • PERT Chart is event-oriented however, CPM Chart is start and completion oriented.
  • PERT is more applicable to research and development projects rather than CPM.

PERT Chart vs Gantt Chart

Both PERT charts and Gantt charts serve as visual aids for project planning, they differ in their applications.

PERT charts, as explained above, were designed to streamline the planning and scheduling of extensive and sophisticated projects. Conversely, Gantt charts are another graphical representation used to plan and schedule projects, dissecting project scope into tasks displayed on a timeline. A Gantt chart facilitates the construction of project timelines, establishment of task dependencies, and visualization of each task’s duration.

PERT Analysis Formula

PERT Method - Program Evaluation and Review Technique Example & Definition (2)

The PERT method employs simple statistic calculations. It uses three-time estimations.

  • Optimistic Estimate: The shortest time required to complete the task.
  • Pessimistic Estimate:The longest time required to complete the task.
  • Most Likely Estimate:The most possible time (probable duration) required to complete the task.

Expected time is calculated with the help of the PERT Analysis formula below

Expected time = ( Optimistic + 4 x Most likely + Pessimistic) / 6

PERT Method - Program Evaluation and Review Technique Example & Definition (3)

Image Source: U.S. Department of the Navy,Program Evaluation Research Task, Summary Report

The PERT Method Implementation Steps

Track the following steps while creating a PERT Chart;

1. List the activities and milestones

The first step is to determine the tasks required to complete the project.

2. Determine the sequence of activities

The second step is to determine the order of the activities. Which activity is the predecessor which one is the successor? It is easy to determine the sequence of some activities however the sequence of some tasks may require deep analysis.

3. Build a network diagram

The third step is to create the network diagram with the help of software or by hand and place the activities on the diagram.

4. Estimate the activity durations

The PERT Method uses three duration estimates for activities which are;

  • Optimistic Estimate
  • Pessimistic Estimate
  • Most Likely Estimate

With the help of three estimates, expected duration is calculated.

5. Determine the critical path

The critical path is the longest path of the network diagram. Forward and backward pass calculations is used to determine the critical path.

The PERT Method Example

We discussed the PERT Definition and how it differs from CPM. Now we will provide a simple PERT Method example with the solution.

In the following example, you are a project manager of a power plant project. You tracked the steps mentioned above and listed the following inputs;

  • All the Activities
  • Predecessors
  • Optimistic, Pessimistic, and Most Likely Activity Durations
    By using “The Pert Formula = (To + 4Tm + Tp)/6”, you calculated the expected duration for each activity.
    All the inputs are listed in the table below.
PERT Method - Program Evaluation and Review Technique Example & Definition (4)

After building a network diagram and estimating the activity durations, you will determine the critical path by making forward and backward pass calculations.
Forward Pass Calculations specify the minimum dates at which each activity can be performed and, ultimately, the minimum duration of a project.

PERT Method - Program Evaluation and Review Technique Example & Definition (5)

Backward Pass Calculations of Program Evaluation and Review Technique determine the latest dates by which each activity can be performed without increasing the project’s minimum duration.

PERT Method - Program Evaluation and Review Technique Example & Definition (6)

After completing the backward pass calculation, you can easily determine the critical path. In project management, “float” or “slack” is the amount of time that a task can be delayed without affecting the deadlines of other subsequent tasks, or the project’s final delivery date. Total float/slack is 0 on the critical path.

PERT Method - Program Evaluation and Review Technique Example & Definition (7)

Total Float: LS – ES = 18-15 = 3
Total Float: LF – EF = 30-27 = 3

The total float can be calculated by subtracting the Early Start date of an activity from its Late Start date or Early Finish date from its Late Finish date.

PERT Method - Program Evaluation and Review Technique Example & Definition (8)

When we analyze the network diagram we will see that there are some paths and every path have duration.
The critical path is the longest path in the network diagram and the total float of the critical path is zero.

Summary

In real life, projects are not executed as it was planned all the time. Risks, unexpected events, uncertainty, and subjective estimates are significant reasons for deviations. PERT Chart is helpful for estimating the project completion time in case of uncertainty. However, it may be difficult to use without software.

In this example, we talked about the PERT definition and calculated the expected duration for each activity and anayzed the difference between PERT and CPM. By making forward, backward calculations, we determined the critical path. Accuracy of expected durations that affect the critical path depends on the optimistic, pessimistic, and most likely duration estimates. With the help of PERT Chart software, it is easy to make these calculations efficiently for many combinations.

External References

Choosing your networking technique

See Also

advantages of gantt chart

PERT Method - Program Evaluation and Review Technique Example & Definition (9)

Irma Gilda

Irma Gilda is chief executive of Sonic Training and Consultancy Co., the training platform offers project planning and scheduling More than 60 k learners have used the platform to attain professional success. Irma is a professional Primavera P6 Trainer.

PERT Method - Program Evaluation and Review Technique Example & Definition (2024)
Top Articles
Why Is Coffee Still Taboo? – Adventist Today
Entitlements
Omega Pizza-Roast Beef -Seafood Middleton Menu
Drury Inn & Suites Bowling Green
Nfr Daysheet
Ub Civil Engineering Flowsheet
Pike County Buy Sale And Trade
10000 Divided By 5
Nestle Paystub
Culvers Tartar Sauce
Craigslist Farm And Garden Cincinnati Ohio
Arboristsite Forum Chainsaw
Nba Rotogrinders Starting Lineups
Cinebarre Drink Menu
Houses and Apartments For Rent in Maastricht
The Exorcist: Believer (2023) Showtimes
Marvon McCray Update: Did He Pass Away Or Is He Still Alive?
Missouri Highway Patrol Crash
My Homework Lesson 11 Volume Of Composite Figures Answer Key
Traveling Merchants Tack Diablo 4
Indystar Obits
Accident On The 210 Freeway Today
Unionjobsclearinghouse
Best Sports Bars In Schaumburg Il
Mini Handy 2024: Die besten Mini Smartphones | Purdroid.de
8000 Cranberry Springs Drive Suite 2M600
Southland Goldendoodles
Bidrl.com Visalia
Giantbodybuilder.com
Weather October 15
Ultra Ball Pixelmon
Craigslist Scottsdale Arizona Cars
Lehpiht Shop
Andhra Jyothi Telugu News Paper
Aliciabibs
Troy Gamefarm Prices
Is Arnold Swansinger Married
Pensacola Cars Craigslist
Daily Times-Advocate from Escondido, California
FREE - Divitarot.com - Tarot Denis Lapierre - Free divinatory tarot - Your divinatory tarot - Your future according to the cards! - Official website of Denis Lapierre - LIVE TAROT - Online Free Tarot cards reading - TAROT - Your free online latin tarot re
Senior Houses For Sale Near Me
Playboi Carti Heardle
Hello – Cornerstone Chapel
Haunted Mansion Showtimes Near Millstone 14
10 Bedroom Airbnb Kissimmee Fl
Autozone Battery Hold Down
Latest Posts
Article information

Author: Frankie Dare

Last Updated:

Views: 6496

Rating: 4.2 / 5 (53 voted)

Reviews: 84% of readers found this page helpful

Author information

Name: Frankie Dare

Birthday: 2000-01-27

Address: Suite 313 45115 Caridad Freeway, Port Barabaraville, MS 66713

Phone: +3769542039359

Job: Sales Manager

Hobby: Baton twirling, Stand-up comedy, Leather crafting, Rugby, tabletop games, Jigsaw puzzles, Air sports

Introduction: My name is Frankie Dare, I am a funny, beautiful, proud, fair, pleasant, cheerful, enthusiastic person who loves writing and wants to share my knowledge and understanding with you.