HS2 | Timeline of a mistreated megaproject (2024)

High Speed 2 (HS2) was supposed to be a game changer for the UK’s transport network, truly ‘levelling up’ neglected parts of the nation and adding capacity to its already oversubscribed railways – after years of revoked promises, it now stands as a sorry symbol for what has happened to the country’s ambition.

With the prime minister due to make a speech at the Conservative Party Conference today in which it is widely believed he will confirm that the Birmingham to Manchester section of the route will be cancelled, NCE takes a look back at the big steps along the way in the rise and fall of the UK’s flagship megaproject.

January 2009 – Creation of High Speed 2 Ltd

After the successful opening of High Speed 1 (HS1) between London and the Channel Tunnel in 2007, with a £5.8bn investment, it appeared the UK had acquired the taste for high speed rail.

The then-Labour government created High Speed 2 Ltd (HS2 Ltd), a non-departmental government body funded by the Department for Transport (DfT) in January 2009 with the remit of investigating a potential route between London and the West Midlands, with a potential to continue to Scotland.

When HS2 Ltd presented its report to the government at the end of 2009, it included possibilities for links to Heathrow Airport, Crossrail (now the Elizabeth Line), the Great Western Main Line and HS1.

March 2010 – HS2 officially revealed

Transport secretary Lord Adonis made the plans official in March 2010, presenting a potential map very similar to that we see now: a London terminus at Euston, a stop at Old Oak Common, an interchange station near Birmingham airport and a central Birmingham station at Curzon Street. This had a price tag of £15.8bn to £17.4bn and construction was unlikely to start before 2017.

Plans for the Y-shaped network with a westward leg to Manchester and an eastward leg to Leeds via the East Midlands and Sheffield were also in consideration at this point.

Opposition parties showed tentative support for the plans – with Conservative shadow transport secretary Theresa Villiers saying that her party would ensure that work started in 2015 if they were in power.

May 2010 – Conservatives come into power

Upon winning the 2010 general election and coming into power as part of a Conservative-Liberal Democrat coalition, the new government ordered a review of the HS2 plans it had inherited. The government was keen for the high speed line to serve Heathrow Airport, but this was rejected by HS2 Ltd.

February 2011 – Public consultation

The HS2 plans for a line between London and Birmingham remained more or less unchanged from those inherited from Labour when they went out to public consultation in February 2011. It was also promised that it would connect to HS1. Later additions would see more high-speed lines north of the West Midlands and high speed links to Heathrow.

The consultation attracted the ire of a range of campaign groups.

January 2012 – Green light

Despite the naysaying, HS2 was officially green lit in January 2012 with a promise to deliver the full Y-shaped network with stations in London, Birmingham, Leeds, Manchester, Sheffield and the East Midlands. It would be delivered in two phases, starting with Birmingham to London and followed by the arms of the Y.

The government also promised that “High speed trains will also connect seamlessly with the existing West Coast and East Coast main lines to serve passengers beyond the HS2 network in Edinburgh, Glasgow, Newcastle, Durham, York, Darlington, Liverpool, Preston, Wigan and Lancaster”.

The press release also stated that “there are no credible alternatives to a new railway line”.

The first services were expected to start in 2026. The sections from Birmingham to Manchester and Leeds would be operational from 2033.

The plans would had to overcome numerous legal challenges and requests for judicial review in the following years, but was not derailed

October - November 2013 – Preparation bill

The High Speed Rail (Preparation) Bill passed with a huge majority in the House of Commons on 31 October 2013 and after scrutiny in the House of Lords received Royal Assent on 21 November. This released funds for surveys and property purchases along the route.

November 2013 – February 2017 – Hybrid bill for Phase One

The government opted to divide the bills for HS2 into two to reflect the two phases of the project. The High Speed Rail (London to West Midlands) Bill was introduced in November 2013 after the preparation bill passed. This was to grant the government permission to build and maintain HS2 and give it the powers to compulsorily acquire properties or land as needed, among other powers.

It went through nearly three years of parliamentary scrutiny before receiving Royal Assent and becoming law in February 2017.

August 2017 – Main contract awards

£6bn of civil engineering works packages for Phase 1 of HS2 were awarded in August following the hybrid bill’s passing into law.

The four consortia were:

  • Skanska Costain Strabag (SCS JV) was awarded the £740M Euston tunnels and the £1bn Northolt Tunnel
  • Carillion Eiffa*ge Kier (CEK JV) won the £742M section from the Chilterns to Brackley and the £616M Brackley to Long Itchington Wood packages
  • Balfour Beatty Vinci (BBV JV) won the £1.32bn Wood Green to Delta Junction and £1.15bn Delta Junction to West Coast Main Line sections
  • Align JV (featuring Bouygues, McAlpine and VolkerFitzpatrick) won the £965M Chiltern Tunnel and Colne Valley Viaduct contract

HS2 Ltd CEO Mark Thurston said at the time: “The contracts we sign today will provide much needed extra capacity and connectivity between our major cities, but it will also unlock huge opportunities for new jobs, homes and economic development and start to rebalance our economy.”

The financial instability of Carillion was known to the government at the time of signing the contracts, with the firm having issued a profit warning three weeks earlier. Transport secretary Chris Grayling said he was assured by partners Kier and Eiffa*ge that it would be able to deliver the contract.

Carillion then went into liquidation in January 2018. The CEK consortium initially became an Eiffa*ge – Kier 50/50 split, but by April 2018 had been bolstered by the additions of Ferrovial and Bam to become EKFB.

June - July 2018 – Civils Delays

The first major speed bump for HS2 came in the summer of 2018 when NCE revealed that HS2 bosses had pushed back the notice to proceed deadline from November 2018 to June 2019. This was to allow the contractors time to cut costs as the estimates were coming in £1bn above target.

The next month the government confirmed the delay, which meant civils work would not start on site until June 2019. At the time, the DfT was still confident that Phase 1 would be delivered on time for 2026 and within budget.

September 2018 – Phase 2b bill delay

The hybrid bill for Phase 2b – Birmingham to Manchester and Leeds – was also pushed back by a year, the government confirmed in September. This was to take account of plans for Northern Powerhouse Rail – another high-speed line connecting the cities of the North that was being developed concurrently.

A DfT spokesperson at the time said: “In order to maximise the huge potential of HS2, it is important to make sure it takes full account of the emerging vision for the other transformative project of Northern Powerhouse Rail.

“Phase 2b of the railway will connect the great cities of the North to boost jobs, housing and economic growth, and remains on track to open in 2033.”

Despite the delay, consultations into equality impact assessments and environmental assessments for phase 2 were launched in October.

October 2018 – Uncertainty emerges

Despite the promise to build the northern legs of HS2, it was not guaranteed and a number of politicians called for it to be scrapped. Jacob Rees-Mogg told NCE that the money would be better spent elsewhere. Then foreign secretary Boris Johnson said that other northern transport projects should take precedence over HS2 phase 2.

HS2 and Crossrail chair Sir Terry Morgan, transport secretary Chris Grayling and Transport for the North chief executive Barry White all urged rail bosses to “make the case” for HS2 Phase 2.

February 2019 – Stations take shape at suspiciously low price

2019 started more positively for HS2. The first designs for the West London transport super hub Old Oak Common were revealed, with Balfour Beatty Vinci Systra JV named as the construction partner. The deal was for £1bn, a cool £350M lower than forecast.

Meanwhile Mace Dragados JV was named as the contractor for the Euston terminus – and had come in with a £1.3bn price, some £300M lower than the forecast.

Bechtel then lodged a legal challenge against HS2 Ltd, claiming that it had accepted an “abnormally low bid” for the Old Oak Common.

Summer 2019 – HS2 weathers the storm

With Theresa May ousted from her position as prime minister in May, the Conservative leadership race took flight through the summer – and saw many pelters thrown at HS2 along the way. Out of the main contenders it was only Jeremy Hunt – ironically – who seemed fully committed to delivering the project.

That month also saw the revelation that the £56bn Phase One was under review to see how – and if – it could be delivered within the budget and timeframes.

August - September 2019 – Oakervee review

When Boris Johnson came into power he quickly ordered former HS2 Ltd chair Doug Oakervee and Rail Freight Federation chair Lord Berkeley to carry out an independent review into the project after reports that the costs had reached £88bn.

This saw a group of contractors write a joint letter to Oakervee warning that “if HS2 is cancelled now, future construction projects across the piece will unfortunately attract an added risk premium. UK construction will cost more”.

It soon emerged that scrapping the eastern leg of Phase 2 – to take the line to Leeds – was being considered as a recommendation from the Oakervee review. Transport for the North was quick to remind of the benefits that its construction would bring.

November 2019 – Government uncertainty around project

A leaked version of Oakervee’s report included the recommendation that the project go ahead in full. However, Lord Berkeley, who was the deputy chair of the review, wrote an open letter criticising this report, saying it had “serious problems with its lack of balance”.

Ahead of the December general election, the Conservative Party released its new manifesto – which excluded any backing of HS2.

January 2020 – No clarity

Even after the Conservatives’ landslide win in the general election, they did not provide any clarity on the situation around HS2. The government was warned by the sector that future projects would cost more if HS2 was axed.

Construction start was not in site and the chance of the 2026 opening being delayed seemed more likely than ever.

February 2020 – Positive news at last

Finally, in February 2020 – alongside the delayed publication of the Oakervee review – the prime minister confirmed that HS2 would go ahead. However, there would be changes to the delivery of HS2 Euston and the northern section was to be repackaged with Northern Powerhouse Rail and “other northern rail projects”. It was also confirmed that timelines would be adjusted.

The industry breathed a sigh of relief at the sign of the green light. The main contractors’ share prices soared.

The government also published its terms of reference for the now-infamous Integrated Rail Plan for the Midlands and the North, which would provide certainty in its plans to invest in the rail network, including HS2, Northern Powerhouse Rail and the Midlands Rail Hub. The government stated that it was “fully committed to providing better rail connectivity between London, the Midlands and the north, ensuring all parts of the country benefit from opportunities for economic development and prosperity”.

The Integrated Rail Plan was promised for publication by the end of 2020.

April 2020 – NTP

The four main contractors on the project were given notice to proceed (NTP) in April.

Amidst a crowd of happy responses, HS2 Ltd CEO Mark Thurston stated: “In these difficult times, today’s announcement represents both an immediate boost to the construction industry - and the many millions of UK jobs that the industry supports - and an important investment in Britain’s future: levelling up the country, improving our transport network and changing the way we travel to help bring down carbon emissions and improve air quality for the next generation.”

However there was still “plenty to do” before construction could officially begin.

May 2020 – More bumps in the road

The positive news of the previous month was tempered in May when the Public Accounts Committee’s update on the project stated that HS2 was “badly off course”, lacking in transparency, low on skills and short on capacity. It was also found that HS2 Ltd’s annual accounts had failed to give an account of the programme’s problems.

Meanwhile, issues around the designs for the Euston tunnels were heard in High Court. A judicial review into the designs was later rejected

September 2020 – Construction officially begins

Having once promised that construction of HS2 would start in 2017, the official commencement of main works was announced in September 2020.

Thurston said: “We are already seeing the benefits that building HS2 is bringing to the UK economy in the short term, but it’s important to emphasise how transformative the railway will be for our country when operational. With the start of construction, the reality of high speed journeys joining up Britain’s biggest cities in the North and Midlands and using that connectivity to help level up the country has just moved a step closer.”

Boris Johnson said: “As the spine of our country’s transport network, the project will be vital in boosting connectivity between our towns and cities.”

October to December 2020 – Fears for Leeds leg re-emerge

Early October 2020 saw design changes revealed for the proposed stations at Manchester Airport and Manchester Piccadilly.

However, the lack of any update to the Leeds leg saw concerns sparked that the government was not committed to it. Regional transport bodies urged commitment from the government. Northern Powerhouse Rail director Tim Wood warned of the risks of axing the eastern arm.

Just before the end of the year, the National Infrastructure Commission warned that a rethink of the Manchester and Leeds stations was needed – with the recommendation being for there to be through stations.

January 2021 – No Integrated Rail Plan

The promised Integrated Rail Plan had not emerged by the end of 2020, and questions remained over whether the eastern leg of HS2 would go forward. Transport for the North continued to campaign for its commitment.

This also cast doubt over the future of Northern Powerhouse Rail.

Meanwhile, HS2 Ltd ordered the designs for Euston to be re-thought. Where it had previously been scoped for 11 platforms and delivered in two phases, it now wanted scaled back plans that would see only 10 platforms delivered but done so in a single phase.

March 2021 – Ups and downs

Things started to look brighter as 2021 continued, with HS2 Ltd announcing that construction of Phase 2a – Birmingham to Crewe – would commence in 2024.

That same month, Align JV started piling works for the Colne Valley Viaduct – the UK’s longest rail viaduct.

It wasn’t all sunny – the National Infrastructure Commission continued to press government on clarity around the Leeds leg in the absence of the Integrated Rail Plan.

The first “schedule pressures” on the project also emerged, forcing a change to the timescales.

May 2021 – Queen in on the act

The uncertainty around the Leeds leg of HS2 was ramped up by none other than the Queen in her speech, where she referenced the future of the project but made no mention of the eastern leg. Rail stakeholders again called for clarity.

The pressure seemingly paid dividends later in the month as transport secretary Grant Shapps promised that the HS2 leg to Leeds would be completed.

May 2021 also saw the first HS2 tunnel boring machine (TBM) launched to drive through the Chilterns, while work also got underway at Old Oak Common.

Summer 2021 – Everything’s fine

Despite growing knowledge that the budget for HS2 was spiralling, the DfT stated to the Public Accounts Committee that the project was still going to be delivered within budget. Nevertheless, the DfT set up a team of construction inspectors to keep tabs on HS2 to ensure it stayed on time and on budget.

In July, HS2 Ltd went full steam ahead in launching procurement for Phase 2b, despite uncertainty around what it would look like. Merely days later, HS2 Ltd launched a review of the commercial case for Phase 2b amidst a materials cost crisis.

Publication of the Integrated Rail Plan was again delayed in July.

Speculation around the future of the eastern leg grew again after a Whitehall source told the media that it was to be axed. Once again, the economic and social benefits of the leg were championed by rail experts and stakeholders.

The DfT published a £3.6bn HS2 contracts pipeline only to pull it down within days after realising it was incorrect. Renewed calls for clarity loudly resounded.

October 2021 – The chops begin

In the surest sign yet that the Leeds leg of HS2 would be cut, the transport secretary claimed that it “no longer benefits people”.

October saw confirmation that Euston would be scaled back from 11 platforms to 10.

November 2021 – Integrated Rail Plan brings bad news

The long awaited Integrated Rail Plan was published on 18 November and confirmed that the eastern leg of HS2 would no longer reach Leeds but instead be curtailed in the East Midlands.

The plan also revealed that Northern Powerhouse Rail had been significantly scaled back.

The rail industry reacted furiously, claiming that it was a “missed opportunity” that hindered levelling up.

The government championed the plan, saying that it would ensure that the rail upgrades “will be delivered sooner than previous plans so that communities, towns and cities across the North and Midlands are better connected with more frequent, reliable and greener services and faster journey times”.

It promised to launch a £100M study into the best way to bring high speed services to Leeds.

December 2021 – Trains chosen

After a long-running legal battle over the procurement for the trains that will run on the high-speed line, HS2 Ltd finally announced that a Hitachi-Alstom JV would provide the rolling stock in a contract worth around £2bn.

January 2022 – Pressing on with Manchester leg

Leaving the Leeds leg in the rearview, the government commenced the new year by starting the parliamentary process of making HS2 Phase 2b by tabling the hybrid bill.

Simultaneously, the government was urged to reconsider the case for an underground through station at Manchester Piccadilly, which had been championed by engineers and rail experts but had not been assessed by the government.

It was also revealed that Mott MacDonald, in a government-commissioned report, had warned that axing the Eastern Leg would mean that HS2 would not meet its strategic priorities.

March 2022 – New Euston

The new designs for Euston station were revealed, with the infamous ‘toenail’ now removed in favour of more prefabricated panels and space for oversight development.

That same month saw the HS2 minister express “concern” as cost pressures on the project rose to £1.7bn.

April 2022 – Golborne link next to go

The first reports that the Golborne link section of the project would be scrapped emerged in April. The Golborne link was a connection between HS2 and the West Coast Main Line that would have added capacity and allowed high speed trains to reach Scotland. Senior Tory MP Sir Graham Brady announced that he had had “categorical, verbal assurances” from Shapps that it would be excised from the plans.

Engineers and stakeholders warned of the value that would be lost by axing the link.

An underground through station at Manchester Piccadilly was categorically ruled out by Shapps late in the month, as he claimed it “doesn’t work out”.

Summer 2022 – Golborne gone

Right up to the day before, government ministers claimed that no decision had been made on the Golborne link, but it was unceremoniously cancelled on 7 June. Cynics claimed that Boris Johnson agreed to the cutting to secure votes in the vote of no confidence against him, which also took place that week.

It was later revealed that £52M had been spent on developing the link before it was axed.

Meanwhile, the Crewe to Manchester hybrid bill passed through its second parliamentary reading. This mean that the petitioning phase would be next and councils in the Manchester area began preparing arguments in favour of changing the bill to provide for an underground through station at Piccadilly.

The first tunnel breakthrough on HS2 was celebrated by BBV in July when the 1.6km drive for the Long Itchington Wood tunnel in Warwickshire was completed.

October-November 2022 – Rumblings

SCS launched its first TBM in October to start driving the first of the London tunnels from West Ruislip to Greenford.

The first rumblings that the HS2 project could be axed emerged this month when Lord Berkeley said that inflation had seen the forecast cost of the project his £155bn. The DfT said there were no plans to cancel.

At the end of the month, levelling up secretary Michael Gove suggested that another funding review of HS2 would possibly be commissioned.

Industry sent a warning to the government ahead of the Autumn Budget when it was feared that cuts to HS2 would be announced, but they did not materialise at this point.

January 2023 – Euston doubts emerge

Early 2023 brought more uncertainty as a report in The Sun revealed that the government was going to make “tough decisions” about HS2. The main one focused around the London terminus at Euston which was rumoured to be delayed or scrapped entirely – which brought vexatious response from the High Speed Rail Group.

February-March 2023 – Euston officially dumped

Reports that the already curtailed eastern leg to the Midlands could also be scrapped to save money emerged.

While these have not (yet) become truth, the rumours around Euston station were solidified in February when transport secretary Mark Harper announced a “re-phasing” of the project by two years. This was decried as a “false economy” by the industry.

Redundancies at the Euston station site started shortly after.

The decision had come after a bombshell report from the National Audit Office called for a “reset” of the Euston project as it was heading to a £4.8bn cost when it had only been budgeted for £2.6bn.

The DfT is currently looking at ways to reduce the scope of the London terminus to bring it back within budget.

Summer 2023 – Sleeves up to finalise Phase 2b plans

The petitioning phase for the Crewe to Manchester hybrid bill got underway in the summer. Stakeholders of all sorts presented their cases to the select committee in extensive sessions to determine the final scope of the route.

Most pressingly, Manchester authorities banded together to argue the case for an underground through station at Manchester Piccadilly. The debate went on for numerous sessions where a 4-platform version was revealed and the tunnelling case was made. The select committee went away to take their time in making a decision about the future of the station.

In July, another bombshell report – this time from the Public Accounts Committee – slammed the government for its failures in the management of the Euston project, saying it “does not know what it is trying to achieve” with the station.

Nearly two years after it was promised in the Integrated Rail Plan, the government finally published the heads of terms for the £100M study for how to better connect Leeds and Bradford.

September 2023 – End of the line for Phase 2

Just when it seemed like HS2 had settled into its final form, the prime minister and chancellor were found out to be discussing the possibility of scrapping the Birmingham to Manchester leg in the hopes of clawing back some money.

While Rishi Sunak has refused to “speculate on rumours”, his poker face is not the best.

There has already been much negative reaction to the reports of its cancellation from stakeholders, engineers and Conservative MPs.

October 2023 - A screeching halt

During his keynote speech at the Conservative Party Conference on 4 October, prime minister Rishi Sunak said that he is “ending this long-running saga [and] cancelling the rest of the HS2 project”.

Dismay was expressed by stakeholders around the country.

Like what you've read?To receive New Civil Engineer's daily and weekly newsletters click here.

HS2 | Timeline of a mistreated megaproject (2024)
Top Articles
How to Find Out the Number of Apex Legends Packs You’ve Opened
Startup Science: The Top 7 Finance Metrics to Evaluate Performance
Ups Stores Near
Television Archive News Search Service
Www.fresno.courts.ca.gov
Robot or human?
Chelsea player who left on a free is now worth more than Palmer & Caicedo
Hk Jockey Club Result
Khatrimaza Movies
Deshret's Spirit
Horned Stone Skull Cozy Grove
Ivegore Machete Mutolation
Busty Bruce Lee
Mini Handy 2024: Die besten Mini Smartphones | Purdroid.de
Alejos Hut Henderson Tx
Ts Lillydoll
Apus.edu Login
Mile Split Fl
Bcbs Prefix List Phone Numbers
Parent Resources - Padua Franciscan High School
Spider-Man: Across The Spider-Verse Showtimes Near Marcus Bay Park Cinema
Ms Rabbit 305
Account Suspended
Aerocareusa Hmebillpay Com
Homeaccess.stopandshop
Plaza Bonita Sycuan Bus Schedule
Foodsmart Jonesboro Ar Weekly Ad
Sensual Massage Grand Rapids
Motorcycle Blue Book Value Honda
Leben in Japan – das muss man wissen - Lernen Sie Sprachen online bei italki
Pronóstico del tiempo de 10 días para San Josecito, Provincia de San José, Costa Rica - The Weather Channel | weather.com
Riverstock Apartments Photos
Tim Steele Taylorsville Nc
Diggy Battlefield Of Gods
Justin Mckenzie Phillip Bryant
Help with your flower delivery - Don's Florist & Gift Inc.
Google Jobs Denver
The Vélodrome d'Hiver (Vél d'Hiv) Roundup
Barber Gym Quantico Hours
WorldAccount | Data Protection
Samantha Lyne Wikipedia
Despacito Justin Bieber Lyrics
Avance Primary Care Morrisville
Ghareeb Nawaz Texas Menu
Martha's Vineyard – Travel guide at Wikivoyage
56X40X25Cm
Deezy Jamaican Food
Tyco Forums
Craigslist Chautauqua Ny
Julies Freebies Instant Win
Competitive Comparison
Latest Posts
Article information

Author: Fr. Dewey Fisher

Last Updated:

Views: 6076

Rating: 4.1 / 5 (62 voted)

Reviews: 93% of readers found this page helpful

Author information

Name: Fr. Dewey Fisher

Birthday: 1993-03-26

Address: 917 Hyun Views, Rogahnmouth, KY 91013-8827

Phone: +5938540192553

Job: Administration Developer

Hobby: Embroidery, Horseback riding, Juggling, Urban exploration, Skiing, Cycling, Handball

Introduction: My name is Fr. Dewey Fisher, I am a powerful, open, faithful, combative, spotless, faithful, fair person who loves writing and wants to share my knowledge and understanding with you.