Construction Damages: Rectification and Betterment | FTI (2024)

Defects are one of the leading causes of disputes and litigation in the construction industry. Most standard forms of contract contain provisions requiring the contractor1 to rectify defects within a stipulated time period. However, given the differing viewpoints and interests of contracting parties, disagreements often arise as to what constitutes a defect, what appropriate remedial action entails, and whether betterment has been obtained. Here, FTI Consulting’s Craig Ballantyne reviews case law to highlight when betterment can be accounted for and how it should be assessed.

“The governing purpose of damages is to put the party whose rights have been violated in the same position, so far as money can do, as if his rights had been observed.”2

In a situation where rectification works have improved a property or asset in some way (i.e. it is larger, newer or has an improved specification), the opposing side will often claim that betterment has been obtained and that a deduction should be made in any award of damages.
In legal terms, a defect is a breach of contract and a common law remedy available to the innocent party is damages.

What is Betterment?

In construction there are two typical approaches used to assess damages. These are:

  • Cost of cure
  • Difference (diminution) in value

The cost of cure is essentially the cost of repair or reinstatement, or to put it another way, the cost of making good of the defects.

Diminution in value is the difference between the fair market value of a property (if the contract had been properly performed) and the fair market value of a property as built, improperly or with its defects.

In cases of defective work, the difference in market value may be problematic to determine and often construction claims are advanced on the basis of the cost of repair or reinstatement.

“Betterment is where, following the repair or reinstatement works, the claimant has a newer or better property than they would have had but for the breach.”

A claimant is generally entitled to the reasonable cost of making good. But what if the property or asset is improved, either because the replacement specification is enhanced, the available products are superior, or the lifecycle and maintenance requirements are improved?

In such circ*mstances, Keating on Construction Contracts3 tells us that:

“A deduction from the damages awarded will usually not be made for betterment if the claimant has no reasonable choice, unless perhaps this would be absurd.”

When Can Betterment Be Accounted For?

No reasonable choice
There are many case examples where a claimant was entitled to recover full repair or replacement costs on the grounds that there was no other reasonable course of action.

One such case is that of The Gazelle,4 where a ship’s engine rotor was damaged in a collision. The claimant replaced the damaged rotor with a new one, thereby extending the engine’s life. The court found that the full cost of repair could be recovered without credit for betterment.

Similarly, in Bacon v Cooper (Metals) Ltd5 a machine known as a ‘fragmentiser’ used to crush scrap metal was damaged by the defendants who had supplied unsuitable scrap material. The damaged rotor was 3.25 years old with a life expectancy of seven years. Again, the court awarded the full repair cost.

While the above cases relate to the repair of assets, similar outcomes can be found in cases relating to the destruction of property.

In Harbutts Plasticine Limited v Wayne Tank & Pump Co Limited,6 Harbutts engaged a contractor to supply and install equipment in its factory. The equipment proved defective and caused a fire which destroyed the factory; however, Harbutts could not rebuild to the original design due to the refusal of planning permission.

The court held that no credit for betterment was required. Widgery LJ stated:7

“The plaintiffs rebuilt their factory to a substantially different design, and if this had involved expenditure beyond the costs of replacing the old, the difference might not have been recoverable, but there is no suggestion of this here. Nor do I accept that the plaintiffs must give credit under the heading of “betterment” for the fact that their new factory is modern in design and material. To do so would be the equivalent of forcing the plaintiffs to invest their money in the modernising of their plant which might be highly inconvenient for them.”

Lord Denning MR agreed, adding that:

“I think they should be allowed the cost of replacement. True it is that they got new for old; but I do not think the wrongdoer can diminish the claim on that account. If they had added extra accommodation or made extra improvements, they would have to give credit. But that is not this case.”8

This judgement also found support in the case of Dominion Mosaics and Tile Co Ltd v. Trafalgar Trucking Co Ltd.9 Here, the claimant’s premises were also destroyed by fire because of the defendant’s negligence. As rebuilding the premises was not a viable option and in order to maintain business operations, the claimant acquired a 36-year lease of another building which had 20% more floor space. The fire also destroyed some nearly new machinery bought by Dominion for a reduced price of £13,500; it was estimated that the machines would cost £65,000 to replace. Dominion had not replaced the machines but claimed £65,000. Dominion was successful in both claims.

In light of these authorities, the commonly held interpretation had been that credit need not be given for betterment when replacing old with new where the claimant had no reasonable choice but to do as he did. In this regard, no reasonable choice would appear to extend to a need to reconstruct to continue business operations or to replace with new where there is no second-hand market for goods.

A clear distinction can be shown in cases where a party has acted through choice. If a claimant rebuilds to a higher standard than strictly necessary through choice, then a deduction for betterment would normally be applied.10

Absurdity (reasonableness)
An alternative view of loss evaluation was put forward in the more recent case of Voaden v Champion,11 a case known as the “Baltic Surveyor”. The judge in this case laid down a test of reasonableness that ought to be applied when assessing the proper measure of damages.

The approach is set out in paragraphs 85 to 89 of the judgement, with the main points summarised below.

  • Cases where a claimant recovers more than he has lost, as may happen where betterment occurs without deduction, ought only to occur in exceptional cases.
  • The exceptional cases envisaged are situations where the betterment claimed has conferred no corresponding advantage to the claimant.12 Though a property may be newer or moderately larger than that which it is replacing, the betterment may give the claimant no advantage.
  • If it can be demonstrated that, for example, a larger property size (or some other aspect of betterment) does confer a monetary advantage to the claimant then this should be considered.13
  • Where there is no second-hand market, betterment will often arise because there is no market mechanism for measuring loss. The test of reasonableness has an important role to play and goes further than the suggestion that replacement with new must be absurd for it to be rejected as a measure of loss. Where an item is old and coming to the end of its life the measure of loss should not be replacement with new (even if no second-hand market exists). Damages should also not be measured as replacement with new where it would not be reasonable to do so.
  • The basic principle is not to physically replace what the claimant has lost but to replace it financially (making the claimant whole in financial terms). The proper approach requires a fact-specific review of what the claimant has lost and an attempt to put a figure on it as best as one can.

How Can Betterment Be Assessed?

There are three common examples of financial benefit obtained following rectification:

  • The property is larger.
  • The property is newer (“new for old”).
  • The specification has been improved.

But when should credit be given and how should it be assessed?
In construction cases, the courts have tended to rely on the opinion of quantum experts when assessing betterment deductions and it is not always possible to identify the basis of the assessment from the judgement.

Some examples of how the courts have approached betterment are provided below.

Larger property
In J Sainsbury v Broadway Malyan, Ernest Green Partnership Ltd,14 the claimant had rebuilt their premises which had been destroyed by fire. The sales area was larger following rebuilding (by 105m2 out of 6,391m2) and the court held that credit must be given.

The court accepted the opinion of one of the quantum experts;15 had the accommodation size been reduced (reflecting the original building size), then the cost of reconstruction could have been reduced by £150,000.

Newer property
In the Baltic Surveyor, the judge concluded that the claimant was entitled to recover damages for the value of a pontoon which had been lost at sea, which was assessed at £16,000. The basis of the assessment was that a replacement pontoon would cost £60,000 and would have a life of 30 years; however, since the old pontoon had just eight remaining years of life expectancy, he awarded 8/30ths of £60,000.

In the Scottish Case of Anderson & Ors v International Oil Pollution Compensation Fund,16 the claimants alleged that the defendants caused damage to their asbestos cement roof while using dispersants to treat an oil spill from a tanker. The court awarded the replacement cost of the roof subject to a betterment deduction.

It was held that betterment should be calculated on the basis of a serviceable life of 55 years despite evidence that manufacturers of this material guaranteed it for only 30 years. The basis of assessment adopted by the court was:17

It was held that betterment should be calculated on the basis of a serviceable life of 55 years despite evidence that manufacturers of this material guaranteed it for only 30 years. The basis of assessment adopted by the court was:

“Taking X to represent the cost of repair at the valuation date and Y to represent the age of the property in years at the same date, I would assess the value of each claim, after deduction for betterment, by the following formula:”

Construction Damages: Rectification and Betterment | FTI (1)

This assessment method would also lead to the same result as the approach adopted in the Baltic Surveyor.

Improved specification
In Tonkin & Anor v UK Insurance Ltd,18 a betterment deduction was made from the damages awarded in relation to the reinstatement costs of an old barn destroyed by fire as several improvements in specification were made, including:

  • Uninsulated brick flooring replaced with insulated oak flooring;
  • Additional dry lining and insulation to walls
  • Roof insulation provided which was not there previously;
  • Central heating system added; and
  • Single glazed windows replaced with double glazed windows.

In Twinmar Holdings Ltd v Klarius UK Ltd & Anor,19 a case concerning a dilapidations claim between a landlord and tenant of a warehouse building and offices, the entrance gates and barrier had been removed, so the tenant was obliged to reinstate them. Although the original posts for the height barrier remained in place, the claimant installed new posts and an opening height barrier. The original barrier was a rigid structure which was slotted over the posts at each end.

The courts found that the replacement barrier represented betterment; it was better because it could open and was more robust. The court awarded one third of the sum originally claimed for the replacement barrier. This was in line with the opinion of one of the experts.

In British Westinghouse Electric & Manufacturing Co Ltd v Underground Electric Railways Co of London Ltd,20 one of the first cases to consider betterment, the turbines and alternators installed by British Westinghouse were found to be defective. They consumed more fuel, generated less power and produced more waste than the contract stipulated.

Underground Electric used the turbines for a few years and even tried to modify them to achieve better performance; however, this proved unsuccessful, and the turbines and alternators were eventually replaced with those from a different manufacturer.

The replacement turbines were more powerful and were also more efficient than the Westinghouse turbines would have been even if they had been as contracted for.

In this case the court held that credit must be given for the betterment obtained.

Industry Examples of Calculating Betterment

A method of calculating betterment that is widely used in the utilities sector is known as the “Bacon Woodrow” formula.

The formula is intended to be used where utility replacement arises due to diversion, and it calculates the financial benefit obtained from the deferment of the time required for renewal of the utility apparatus.

The use of the formula is approved in The New Roads and Street Works Act 199121 Code of Practice for Diversionary Works.22 The formula is provided in Appendix E of the Code of Practice (“CoP”) and is set out below for reference.

Construction Damages: Rectification and Betterment | FTI (2)

The financial benefit calculated is the interest saved on capital expenditure through the deferment of the time required for renewal. The results using this method of assessment can be contrasted with the calculation in the Baltic Surveyor. To recap, in the Baltic Surveyor an assessment was made of what was lost (i.e. a pontoon with eight years remaining life expectancy). This meant the plaintiff was awarded 8/30ths of the £60,000 replacement cost.

The two methods of assessment can produce very different results. Take for example, a situation where equipment was replaced that was 50 years old, had a life expectancy of 100 years and cost £500,000 to replace. The award following deduction for betterment/financial benefit derived by applying each method is set out below.

Construction Damages: Rectification and Betterment | FTI (3)

While Appendix E of the CoP relates to betterment obtained for the deferment of renewal, Appendix F (itself titled ‘Betterment’) sets out other occasions where financial benefit should be credited. The two scenarios put forward are:

a) When increasing the capacity of the apparatus (except where due to using the nearest available size); and
b) When using material which enhances network capability (not including material which is in present day use for the same duty).

In these examples the CoP proposes that betterment is assessed as the difference between the cost of laying the increased capacity or enhanced duty apparatus and the estimated cost of laying the same capacity or the same duty.

Focusing on the Facts

For an award of damages to be reduced for betterment it is necessary to show that the claimant has received some form of financial benefit or advantage.23 The mere fact that something is newer or larger may not be sufficient.

“It is necessary to consider what is reasonable to make the claimant whole in financial terms and this will involve a fact-specific review of what has been lost.”

It should be a rare occasion that a claimant is placed in a better position than he would have been without the breach; however, exceptions will always exist. If, for example, improvements are a result of complying with statutory requirements current at the time of rectification, would it be reasonable for a damages award to be reduced?

There is no one size fits all solution; when it comes to the valuation of betterment, it is left open to parties, typically through their quantum experts, to persuade the courts on the most appropriate method to apply, depending on the precise facts in each case.

Footnotes:

1. During the course of construction and the defects liability period

2. Asquith L.J. in Victoria Laundry Ltd v. Newman Ltd [1949] 2 K.B. 528 at 539, CA

3. Keating on Construction Contract 10th Edition at 9-076

4. (1844) 2 W Rob 279

5. [1982] 1 All ER 397

6. [1970] 1 QB 447

7. Ibid, 473B

8. Ibid, 468A

9. [1990] 2 All ER 246

10. Richard Roberts v. Douglas Smith Stimson (1988) 46 B.L.R. 50 at 69; see also Tonkin & Anor v UK Insurance Ltd [2006] EWHC 1120 (TCC) where a betterment deduction was made from the damages awarded in relation to the reinstatement costs of an old barn destroyed by fire as a number of improvements in specification were made to the reconstructed barn.

11. [2002] EWCA Civ 89

12. The exceptional cases cited are those raised earlier in this article. Namely, The Gazelle and Bacon v Cooper (in relation to the repair of chattels) and the Harbutts and Dominion cases (in relation to the destruction of buildings where replacement is necessary to prevent collapse of the business or loss of profits).

13. This follows the decision in British Westinghouse v Underground Electric Railways, where defective machines were replaced with new machines of superior efficiency.

14. [1998] EWHC Technology 302

15. The precise method of assessment is not stated.

16. [2001] Scots CS 34

17. Ibid, 247

18. [2006] EWHC 1120 (TCC)

19. [2013] EWHC 944 (TCC) (19 April 2013)

20. [1912] AC 673 (HL)

21. The New Roads and Street Works Act 1991 (NRSWA), supported by relevant Regulations and Codes of Practice, provides a legislative framework for street works by undertakers (including utility companies) and works for road purposes – to the extent that these must be co-ordinated by street authorities.

22. Diversionary works is a term associated with projects that involve utilities. Diversionary works are sometimes required to accommodate highway improvement schemes and may be used when it becomes necessary to reroute utility services.

23. The evidential burden of demonstrating betterment lies with the defendant see: Oswald v Countrywide Surveyors Ltd (1996) 50 Con. L.R. 144.

Related Insights

  • The Value of Expert Opinion for Quantum and Delay in Construction Arbitration Read Article
  • Claim Everything. Explain Nothing. Deny Everything Read Article
  • What We Know Already – Fact is King Read Article

Related Information

  • Dispute Resolution
Construction Damages: Rectification and Betterment | FTI (2024)

FAQs

What is betterment in construction claims? ›

“Betterment is where, following the repair or reinstatement works, the claimant has a newer or better property than they would have had but for the breach.” A claimant is generally entitled to the reasonable cost of making good.

What is a rectification in construction? ›

No matter the experience or skill of the contractor, many employers will eventually ask them to return to carry out rectification works. This involves correcting errors made during construction and ensuring that the project is completed to a high standard.

What is the betterment rule? ›

The Betterment Defense

If a builder or contractor is making repairs, the owner can ask the contractor to provide an upgrade from what was contracted for originally—but the owner would have to pay the difference in the upgrades.

What is the betterment or added benefit defense? ›

The betterment, or added benefit, doctrine is widely used in construction cases to defend against outrageous damages. It can be argued in response to claims of breach of contract, as well as claims of negligence.

What is betterment vs repairs and maintenance? ›

Betterments are treated as tangible capital assets (set up as a sub-number of the related asset) and amortized accordingly. Replacements are treated as ordinary operating expenditures. The cost incurred in the maintenance of the service potential of a tangible capital asset is a repair, not a betterment.

What is the legal definition of betterment? ›

An increase in the value of a property as a result of action or proposed action by a public body. This could be positive action, such as the construction of a new road benefiting the property, or negative, as where restrictions are imposed on another property.

What is the rule of rectification? ›

Rectification is an equitable remedy by which the court can correct an error of expression where a written document does not match the parties' intention. It is available only in relation to written contracts and other documents. An oral agreement cannot be rectified.

What is an example of rectification? ›

Rectification is any process that converts a bidirectional flow into a unidirectional flow. The ratchet wrench makes unidirectional rotation by slipping in the reverse direction instead of passing the reverse motion through to the load. Another example is a simple bottle style fish trap.

What are the two methods of rectification? ›

Rectifiers are pivotal components in electronic devices, converting AC voltage to DC voltage; half-wave rectifiers focus on simplicity, allowing one half of the AC cycle that results in lower efficiency, whereas full-wave rectifiers utilize both halves, offering higher efficiency and a smoother DC output.

What are the rules of Betterment? ›

What is Betterment? A tenant has a duty of care to look after a property and return it to the landlord in the same condition it was at the start of the tenancy – allowing for fair wear and tear. Landlords cannot expect their property to be returned in a better condition than it was at the start.

What is a Betterment claim? ›

In an auto insurance policy, betterment refers to the policy condition that your insurer is not obligated to pay for any repairs or replacements which result in a vehicle's improvement over the quality that existed before an accident.

What are the requirements for Betterment? ›

All customers must be at least 18 years of age in order to consent to all our agreements. Customers must have a permanent U.S. address, a U.S. Social Security Number or an ITIN, and a ... What is Betterment and how does it work?

What is betterment in construction? ›

The concept of betterment generally arises when in the course of making repairs to defective work an owner adopts a more expensive design or includes other enhancements that give the owner a “better” project than it would have otherwise received.

What is the legal defense of betterment? ›

Betterment depends on what is reasonable. If an improvement is necessary and reasonable to complete the terms of a contract, then it will be allowed. If it is unreasonable, it will be considered betterment; thus, the amount of damages that constitute the upgraded improvement is not allowed.

What is considered a betterment? ›

The betterment of something is the act or process of improving its standard or status. [formal] His research is for the betterment of mankind. Synonyms: improvement, gain, advancement, enhancement More Synonyms of betterment.

What is improvements and betterments in insurance terms? ›

“Improvements and betterments” typically are defined as fixtures, alterations, additions or installations made a permanent part of a building by and at the expense of the tenant, which may not legally be removed.

What is betterment and first cost? ›

The doctrines of betterment and first costs prevent this—costs for “bettering” a non-breaching party's position should be excluded from a damages calculation. In other words, the non-breaching party is not gifted a blank check to fix a problem it otherwise would have had to pay for at the outset.

What is QIP in construction? ›

Qualified Improvement Property is defined as any improvement made to the interior of a nonresidential building after the building is placed in service. Improvements must explicitly exclude expansion of the building, elevators and escalators, and changes made to a building's internal structural framework.

What is betterment in Florida law? ›

“Betterment” occurs when an owner makes repairs with a more expensive design, uses higher quality materials, or increases the defective building or component's useful life. Grossman v. Sea Air Towers, Ltd., 513 So. 2d 686, 688 (Fla.

Top Articles
When To Use A Personal Loan To Pay Off Credit Card Debt | Bankrate
Synchronous vs. Asynchronous Programming: What You Need to Know
$4,500,000 - 645 Matanzas CT, Fort Myers Beach, FL, 33931, William Raveis Real Estate, Mortgage, and Insurance
Kostner Wingback Bed
AllHere, praised for creating LAUSD’s $6M AI chatbot, files for bankruptcy
Blorg Body Pillow
Housing near Juneau, WI - craigslist
Odawa Hypixel
Danielle Moodie-Mills Net Worth
855-392-7812
Couchtuner The Office
Senior Tax Analyst Vs Master Tax Advisor
Green Bay Press Gazette Obituary
Detroit Lions 50 50
Cvb Location Code Lookup
Weather Rotterdam - Detailed bulletin - Free 15-day Marine forecasts - METEO CONSULT MARINE
Roll Out Gutter Extensions Lowe's
Nearest Walgreens Or Cvs Near Me
Allybearloves
Sussur Bloom locations and uses in Baldur's Gate 3
Wbiw Weather Watchers
Boscov's Bus Trips
Somewhere In Queens Showtimes Near The Maple Theater
Optum Urgent Care - Nutley Photos
Avatar: The Way Of Water Showtimes Near Maya Pittsburg Cinemas
R Baldurs Gate 3
O'reilly's In Monroe Georgia
897 W Valley Blvd
Winterset Rants And Raves
Gabrielle Enright Weight Loss
How does paysafecard work? The only guide you need
Drabcoplex Fishing Lure
Cross-Border Share Swaps Made Easier Through Amendments to India’s Foreign Exchange Regulations - Transatlantic Law International
CVS Near Me | Somersworth, NH
Sadie Sink Doesn't Want You to Define Her Style, Thank You Very Much
Henry County Illuminate
National Insider Threat Awareness Month - 2024 DCSA Conference For Insider Threat Virtual Registration Still Available
3496 W Little League Dr San Bernardino Ca 92407
One Main Branch Locator
2007 Peterbilt 387 Fuse Box Diagram
Craigslist Pets Plattsburgh Ny
Kent And Pelczar Obituaries
Rush Copley Swim Lessons
Big Reactors Best Coolant
Reli Stocktwits
2000 Ford F-150 for sale - Scottsdale, AZ - craigslist
Naomi Soraya Zelda
Gear Bicycle Sales Butler Pa
Craigslist Monterrey Ca
Factorio Green Circuit Setup
Latest Posts
Article information

Author: Kimberely Baumbach CPA

Last Updated:

Views: 6396

Rating: 4 / 5 (41 voted)

Reviews: 88% of readers found this page helpful

Author information

Name: Kimberely Baumbach CPA

Birthday: 1996-01-14

Address: 8381 Boyce Course, Imeldachester, ND 74681

Phone: +3571286597580

Job: Product Banking Analyst

Hobby: Cosplaying, Inline skating, Amateur radio, Baton twirling, Mountaineering, Flying, Archery

Introduction: My name is Kimberely Baumbach CPA, I am a gorgeous, bright, charming, encouraging, zealous, lively, good person who loves writing and wants to share my knowledge and understanding with you.